MIS06-00191
| FIR-Final | 8/3/2006 | 8/3/2006 | 8/4/2006 10:41:13 AM | P | FAIL |
|
|
Need to post max occupant load sign, provide signage above the main entry/exit door "this door to remain unlocked while building is occupied", provide K class extinguisher with current tag for the cooking hood area, NOTE: modifications to the hood system have been made-will require a permit and inspection for approval of this work.
|
BLD06-00863
| FIRE-Final Inspection | 8/3/2006 | 8/3/2006 | 8/3/2006 3:48:58 PM | P | PASS |
|
|
c/n items are complete, final fire life safety inspection passed.
|
FIR06-00494
| INSP-Final Inspection | 8/2/2006 | 8/3/2006 | 8/3/2006 3:48:06 PM | A | PASS |
|
|
Fire alarm permit passed, note: record of completion forms not available for signature on site.
|
FIR06-00481
| INSP-Final Inspection | 8/3/2006 | 8/3/2006 | 8/3/2006 3:45:31 PM | P | PASS |
|
|
Items on previous c/n have been verified for completion, fire sprinkler permit finaled.
|
FIR05-00536
| INSP-Sprinkler Rough-in | 8/3/2006 | 8/3/2006 | 8/3/2006 3:21:45 PM | P | PART |
|
|
UG connection for remote FDC passed inspection for cover.
|
FIR05-00425
| INSP-Sprinkler Rough-in/Hydro | 8/2/2006 | 8/3/2006 | 8/3/2006 3:19:48 PM | P | PART |
|
|
OH inspection for cover at the drop ceiling areas in the 1st floor hotel lobby are good for cover- noted corrections at this location have been completed, noted one sw at garage door west side is too low as installed. Also inspected 6th floor guest room adjacent to temp elevator for rough-in.
|
FIR06-00525
| INSP-Final Inspection | 8/3/2006 | 8/3/2006 | 8/3/2006 12:22:24 PM | P | PASS |
|
|
Fire sprinkler work is complete for final, inspection passed.
|
FIR06-00525
| INSP-Sprinkler Rough-in | 8/3/2006 | 8/3/2006 | 8/3/2006 12:21:14 PM | P | PART |
|
|
OH sprinkler rough-in installation is acceptable.
|
FIR05-00503
| FIR-Aging Inspection | 8/3/2006 | 8/3/2006 | 8/3/2006 11:53:52 AM | | DEFR |
|
|
|
FIR06-00321
| INSP-Sprinkler Rough-in/Hydro | 8/3/2006 | 8/3/2006 | 8/3/2006 11:53:38 AM | P | DEFR |
|
|
Contact: Todd - Need UG & OH Hydro Test; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Inspection rescheduled
|
BLD06-01257
| FIRE-Final Inspection | 8/2/2006 | 8/3/2006 | 8/3/2006 11:49:40 AM | A | PASS |
|
|
Fire life safety is satisfactory, inspection passed.
|
FIR06-00434
| INSP-Supply line flush | 8/2/2006 | 8/3/2006 | 8/3/2006 10:06:00 AM | A | PART |
|
|
UG supply line flush performed satisfactory.
|
FIR05-00037
| INSP-Final Inspection | 8/2/2006 | 8/3/2006 | | P | |
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|