FIR14-00603
| INSP-Sprinkler Rough-in | 8/3/2015 | 8/3/2015 | 8/4/2015 12:42:25 PM | P | CANC |
|
|
Due to time constraints, this inspection could ntot be completed. Will reschedule for 8/4.
|
FIR14-00815
| INSP-Sprinkler Rough-in | 8/3/2015 | 8/3/2015 | 8/4/2015 12:34:04 PM | P | PASS |
|
|
This is a trip test dry system trip for 4/1 north.
|
FIR14-00898
| INSP-Final Inspection | 8/3/2015 | 8/3/2015 | 8/4/2015 12:28:26 PM | P | CANC |
|
|
Canceled fire alarm testing for today - rescheduled for tomorrow (8/4).
|
BLD13-02424
| FIRE-Conference | 8/3/2015 | 8/3/2015 | 8/4/2015 12:26:11 PM | P | DONE |
|
|
\Meeting with GC and Elect. contractor to review exit signs for clubhouse, corridors, and parking garage. See plans for areas where additional signs are required, and where exit signs need to be relocated.
|
FIR14-00815
| INSP-Final Inspection | 8/3/2015 | 8/3/2015 | 8/3/2015 2:15:49 PM | P | CANC |
|
|
Final inspection pending completion and passing of all dry pipe systems.
|
FIR13-00724
| INSP-Alarm Testing | 7/30/2015 | 8/3/2015 | 8/3/2015 2:14:26 PM | P | CANC |
|
|
No inspections called in for this permit.
|
FIR14-00365
| INSP-Sprinkler Rough-in/Hydro | 7/31/2015 | 8/3/2015 | 8/3/2015 2:13:01 PM | P | PASS |
|
|
Fire pump commissioning test with MFG's rep. Tested 0 flow. 100% and 150% with generator and both supplies open. All tested OK. Pump test report to e emailed to Tim Frost.
|
FIR14-00813
| INSP-Final Inspection | 7/31/2015 | 8/3/2015 | 8/3/2015 2:10:55 PM | P | CANC |
|
|
6th floor H&D system not ready for test yet. Exhaust system not completed.
|
FIR14-00328
| INSP-Final Inspection | 7/31/2015 | 8/3/2015 | 8/3/2015 2:10:00 PM | P | PART |
|
|
First floor kitchen hood and duct system test, including balloon test, MP, detection gas/electric shutoffs, nozzles types, etc. Alltested OK NOTE: Nozzle placement may have to be modified to point in the locations per the manual (center of appliance). Also, may need to have a barier between the DF fryer and the gas range - currently 6" with no barrier.
|
FIR13-00724
| INSP-Alarm Testing | 7/30/2015 | 8/3/2015 | 8/3/2015 2:07:06 PM | A | PART |
|
|
Initial fire alarm system testing, including test of notification (speaker/strobes) throuout the JUMP bldg. including the U/G parking garage the above ground parking garage, the helix and all rooms above grade. A few devices were not very load, and the contractor agreed to modify the devices in these areas to improve audibility. Also tested fire pump functions to coincide with the fire pump commissioning test. Also tested one (1) H&D system test for the 1st floor kitchen. NOTE: Elevators, HVAC, and FSDs not ready for test yet.
|