MEC18-03753
| Rough-in | 8/2/2018 | 8/3/2018 | 8/3/2018 3:39:28 PM | P | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Devony Bullard- supply run above front door still needs flex fixed- lineset coming down exterior wall needs fixed- duct work at furnace needs sealed
|
MEC18-03754
| Rough-in | 8/2/2018 | 8/3/2018 | 8/3/2018 3:34:43 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Devony Bullard-20lb gas pressure test ok- R/I ok
|
MEC18-03776
| Final | 8/2/2018 | 8/3/2018 | 8/3/2018 2:45:37 PM | P | NR |
|
|
Please call on way: Blake ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss
|
MEC18-03776
| Pressure Test | 8/2/2018 | 8/3/2018 | 8/3/2018 2:44:35 PM | P | NR |
|
|
Please call on way: Blake ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss
|
MEC18-03794
| Rough-in | 8/3/2018 | 8/3/2018 | 8/3/2018 2:36:20 PM | P | NR |
|
|
Phone #: ###-#### Inspection requested via web by Aaron Toomey- crawl not finished- lineset not roughed in- indoor equipment not set-
|
MEC18-03794
| Pressure Test | 8/3/2018 | 8/3/2018 | 8/3/2018 2:34:32 PM | P | PASS |
|
|
and fireplace Phone #: ###-#### Inspection requested via web by Aaron Toomey- 20lb gas pressure test ok- 5lb flue pressure test ok
|
MEC18-03590
| Final | 7/30/2018 | 8/3/2018 | 8/3/2018 2:07:22 PM | P | PASS |
|
|
Homeowner Mark Hirsch ###-#### Phone #: ###-#### Inspection requested via web by Mary LaFayette- furnace ac coil co ok
|
MEC18-03799
| Final | 8/3/2018 | 8/3/2018 | 8/3/2018 1:50:32 PM | P | PASS |
|
|
Please call on way: Craig ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss- furnace ac coil co ok
|
MEC18-03768
| Final | 8/3/2018 | 8/3/2018 | 8/3/2018 1:41:25 PM | P | FAIL |
|
|
final inspection for replacement a/c, horizontal coil, line set, condensate, ; moved 2 registers. Phone #: ###-#### Inspection requested via web by SOPHIA FLEMING- need to seal lineset penetration- need to also add other for duct work added
|
MEC18-03092
| Final | 8/2/2018 | 8/3/2018 | 8/3/2018 1:19:19 PM | P | PASS |
|
|
Please call Gabby prior to inspection. ###-#### Phone #: ###-#### Inspection requested via web by Mary LaFayette- furnace ac coil co ok
|
MEC18-02077
| Rough-in | 8/2/2018 | 8/3/2018 | 8/3/2018 12:10:37 PM | A | PART |
|
|
seal inspection--see Richard on sie Inspection requested via web by Steve Torgerson- duct seal ok- have questions on return plenum and type of wire ran within the plenum
|
MEC18-03294
| Final | 8/2/2018 | 8/3/2018 | 8/3/2018 10:38:23 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Mary LaFayette- furnace ac coil co ok
|
MEC18-03376
| Final | 8/1/2018 | 8/3/2018 | 8/3/2018 10:22:11 AM | A | PASS |
|
|
Tenant property Phone #: ###-#### Inspection requested via web by Justin Osterhout- electric furnace ac coil ok
|
MEC18-02605
| Final | 8/2/2018 | 8/3/2018 | 8/3/2018 10:01:30 AM | A | PART |
|
|
call prior to arriving so we can be onsite Phone #: ###-#### Inspection requested via web by Nicholas Paige- 103,106,125,134,138,117,118,216,205,,237, 242, final ok 1st phase- 2nd phase will be 9 rooms- total on this permit will be 20 rooms
|
MEC18-01990
| Final | 8/2/2018 | 8/3/2018 | 8/3/2018 9:32:49 AM | A | PASS |
|
|
duct blast witness at 9am, Logan will be there to let you in. thanks Phone #: ###-#### Inspection requested via web by Gary Reeves- duct blast ok- final ok
|
MEC18-01959
| Final | 8/2/2018 | 8/3/2018 | 8/3/2018 9:32:29 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Ashley Stegemann- fireplace final ok
|
MEC17-05362
| Final | 8/2/2018 | 8/3/2018 | 8/3/2018 8:54:06 AM | A | PASS |
|
|
BRIAN IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- final ok
|