Inspections for the day of: Monday, August 3, 2020.
Number of inspections: 17
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTom Saunders
TitleELE-INSPECTOR
Phone #208-794-1923
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE20-02706 Permanent Service8/3/20208/3/20208/3/2020 2:40:45 PMPPASS
Jeff Phone #: ###-####..
meter to all in one...panel inside garage replaced and made a sub panel
p/s u/g reconnect ok
ELE20-00449 Electrical Rough-In8/3/20208/3/20208/3/2020 1:53:46 PMPPASS
We need an above ceiling inspection in the Lobby. We are ready now Phone #: ###-#### Inspection requested via web by Kerri Hamilton...
lobby grid and rm 106 grid...ok to cover
ELE20-02597 Electrical Rough-In8/3/20208/3/20208/3/2020 1:20:00 PMPPASS
Electrical rough-in inspection of new music room. Call Paul with questions or issues. ###-####. Phone #: ###-#### Inspection requested via web by Joe McLean....

new furred out walls
new walls added
ok to cover
ELE20-02696 Temporary Service8/3/20208/3/20208/3/2020 11:47:46 AMPPASS
Phone #: ###-#### Inspection requested via web by Troy Ballard...
t/s u/g new ok
ELE20-02700 Temporary Service8/3/20208/3/20208/3/2020 11:47:13 AMPPASS
Phone #: ###-#### Inspection requested via web by Troy Ballard...
t/s u/g new ok
ELE20-02701 Temporary Service8/3/20208/3/20208/3/2020 11:46:50 AMPPASS
Phone #: ###-#### Inspection requested via web by Troy Ballard...
t/s u/g new ok
ELE20-02698 Temporary Service8/3/20208/3/20208/3/2020 11:46:25 AMPPASS
Phone #: ###-#### Inspection requested via web by Troy Ballard...
t/s u/g new ok
ELE20-02699 Temporary Service8/3/20208/3/20208/3/2020 11:45:49 AMPFAIL
Phone #: ###-#### Inspection requested via web by Troy Ballard....

all temporary receptacles shall have GFCI protection...240v recp
ELE20-02703 Temporary Service8/3/20208/3/20208/3/2020 11:44:19 AMPPASS
Phone #: ###-#### Inspection requested via web by Troy Ballard...
t/s u/g new ok
ELE20-02702 Temporary Service8/3/20208/3/20208/3/2020 11:43:53 AMPPASS
Phone #: ###-#### Inspection requested via web by Troy Ballard...

t/s u/g new ok
ELE20-02697 Temporary Service8/3/20208/3/20208/3/2020 11:22:21 AMPPASS
Phone #: ###-#### Inspection requested via web by Troy Ballard...
t/s u/g new ok
ELE20-02706 Conference8/3/20208/3/20208/3/2020 10:46:30 AMPPASS
Jeff Phone #: ###-####,,,discussed service change...competent in work
ELE20-02680 Electrical Rough-In7/31/20208/3/20208/3/2020 10:19:36 AMAPASS
Please call Mitch Whited 30 minutes prior Phone #: ###-#### Inspection requested via web by Mitch Whited...

remodel kitchen..added cans and required recps for counter...ok to cover
ELE20-02052 Final7/31/20208/3/20208/3/2020 10:04:13 AMANR
I would like to meet you there. Every thing is done except the service. Still waiting on Idaho power. Call and we can go over it Phone #: ###-#### Inspection requested via web by Neal Rumsey...

unable to do partial final and give temp occupency ...service needs completed before any type of final given
ELE20-02692 Electrical Rough-In8/2/20208/3/20208/3/2020 9:34:49 AMAPASS
new circiuts are stubded under house. they will be extended to main power box on trim. Phone #: ###-#### Inspection requested via web by ron spen cer...

rough ok to cover...new mst bedroom/mst bath
ELE20-01806 Final8/2/20208/3/20208/3/2020 9:00:26 AMAPASS
Phone #: ###-#### Inspection requested via web by Tyler Ridley...ok to final
ELE20-00724 Electrical Rough-In8/3/20208/3/20208/3/2020 8:29:39 AMAPASS
Contact: Jeremy Thornock. underground inspection please Phone #: ###-#### Inspection requested via web by Deb Gooden...

perimeter underground of building