Inspections for the day of: Friday, August 30, 2002.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR02-00249 INSP-Final Inspection8/26/20028/30/20028/30/2002 12:00:00 AMACANC
cancelled by contractor 8/30/2002 8:04:12 AM
FIR02-00178 INSP-Supply line flush8/29/20028/30/20028/30/2002 12:00:00 AMAPASS
underground supply line flush and hydro test OK 8/30/2002 10:40:36 AM
BLD02-00311 FIRE-Conference8/29/20028/30/20028/30/2002 12:00:00 AMANR
No approved plans on site and it doesn't appear the plans have even been submitted 8/30/2002 12:30:42 PM
BLD02-01648 FIRE-Final Inspection8/29/20028/30/20028/30/2002 12:00:00 AMAPASS
fire life/safety finaled 8/30/2002 9:57:40 AM
FIR02-00244 INSP-Final Inspection8/29/20028/30/20028/30/2002 12:00:00 AMAFAIL
"work room" will be used as storage and therefore will be considered ordinary hazard occupancy which means the sprinkler pendants are overspaced. 130sq ft max. Also the shelves only allow 16" of clearance instead of the 18" required. The sprinklers will need to be space to the shelves 8/30/2002 2:34:31 PM