FIR05-00737
| FIR-Aging Inspection | 8/30/2006 | 8/30/2006 | 9/6/2006 3:29:50 PM | | DONE |
|
|
On site visit to determine status of work which is still in progress.
|
BLD06-01932
| FIRE-Final Inspection | 8/30/2006 | 8/30/2006 | 8/30/2006 2:54:39 PM | P | PASS |
|
|
c/n items have been completed, inspection passed.
|
FIR06-00514
| INSP-Final Inspection | 8/30/2006 | 8/30/2006 | 8/30/2006 2:53:51 PM | P | PASS |
|
|
Fire sprinkler permit finaled.
|
FIR06-00604
| INSP-Alarm Testing | 8/29/2006 | 8/30/2006 | 8/30/2006 2:53:22 PM | P | PASS |
|
|
Fire alarm passed field inspection, permit finaled.
|
FIR06-00538
| INSP-Final Inspection | 8/29/2006 | 8/30/2006 | 8/30/2006 2:28:28 PM | P | PART |
|
|
Visual notification is lacking in one area due to architectural changes not reflected on approved plans, some portions of the alarm work as outlined in the scope of work are not completed for testing at this time, list of signals recieved for devices tested today to be made available prior to next inspection.
|
FIR06-00537
| INSP-Final Inspection | 8/29/2006 | 8/30/2006 | 8/30/2006 2:18:55 PM | P | PART |
|
|
Provide signage at the door to the FACP room, provide lock at the panel breaker, duct detectors for HVAC unit shutdown are not completed for testing, elevator is not installed (associated devices not tested). Control panel, pull stations, ID detectors for fire dampers, and notification devices for the 1st floor tested okay.
|
FIR06-00533
| INSP-Final Inspection | 8/30/2006 | 8/30/2006 | 8/30/2006 1:13:03 PM | P | FAIL |
|
|
Missing ceiling tile and escutcheon at one location in the dry storage room.
|
BLD06-01416
| FIRE-Final Inspection | 8/30/2006 | 8/30/2006 | 8/30/2006 1:11:38 PM | P | FAIL |
|
|
Need to post max. occupant load sign per review comments, repair door leaf at the north entry/exit doors, install missing ceiling tile and sprinkler escutcheon at the dry storage room, provide one additional PFE for the back office and storage area as discussed.
|
BLD06-00879
| BLD-Other | 8/29/2006 | 8/30/2006 | 8/30/2006 12:27:50 PM | A | FAIL |
|
|
Scope of work is not completed at this time including some restrooms, elevator and shaft, some fire alarm work, existing fire sprinkler system needs a current annual inspection, project is not ready for final life safety inspection.
|
BLD06-01398
| BLD-Other | 8/29/2006 | 8/30/2006 | 8/30/2006 12:23:13 PM | A | FAIL |
|
|
Several items related to fire life safety are still outstanding, project is not ready for final inspection at this time.
|
BLD06-01128
| BLD-Other | 8/29/2006 | 8/30/2006 | 8/30/2006 12:21:47 PM | A | FAIL |
|
|
Fire life safety is not completed at this time.
|
BLD06-01127
| BLD-Other | 8/29/2006 | 8/30/2006 | 8/30/2006 12:20:24 PM | A | FAIL |
|
|
Fire extinguishers are not installed, missing door hardware, need suite addresses, floor and ceiling tile are not completed, need to approve fire alarm prior to life safety final, scope of work is not completed.
|
FIR06-00432
| INSP-Final Inspection | 8/29/2006 | 8/30/2006 | 8/30/2006 7:31:47 AM | A | CANC |
|
|
Contact: Chris Felty; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|