Inspections for the day of: Wednesday, August 30, 2006.
Number of inspections: 15
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDixie Fellows
TitleMEC-COM/RES INSPECTOR
Phone #794-6208
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC06-02742 Conference8/30/20068/30/20068/30/2006 8:56:33 PMPPEND
for Dixie Mae only inpsection for conference..met with jd and discussed that this job is no longer just a change-out of equipment. home-owner was required to have a building permit due to structural changes. i told jd they would need to add supply and r/a as well as comb air to furnace. if they didn't want to continue the job we could final their portion of the work and the home-owner can hire another contractor to bring the rest up to code as is required by the irc. i tried to explain to him this was no longer just a change-out but a remodel and the differences required by the code..dixie
MEC06-00544 Final8/30/20068/30/20068/30/2006 8:51:41 PMPFAIL
###-####..need 18" clearance from cabinets on both sides of range to counter top..gas shut-off valve at gas range to be readily accessible..comb air termination outside to small due to size of grill and louvers..make sure general contractor has fixed his clearances at range before you recall this..thanks dixie
MEC06-00544 Conference8/30/20068/30/20068/30/2006 8:09:44 PMPFAIL
MPI 18th st. ; Phone #: ###-#### x201 Internet Inspection Request from: Sickles Cassi...this should have been called for a final..so i scheduled it...dixie
MEC06-00427 Final8/28/20068/30/20068/30/2006 8:07:39 PMANR
Trout - Chris Williams ; Phone #: ###-#### x202 Internet Inspection Request from: Sickles Cassi...i need a contact # to get me on the roof
MEC06-02175 Conference8/28/20068/30/20068/30/2006 8:04:14 PMAPASS
CALL DON TO SCHEDULE; Phone #: ###-#### Internet Inspection Request from: Allison Briggs..discussed some issues before final..s/f dampers, duct detectors, flex duct, etc
MEC06-02176 Conference8/28/20068/30/20068/30/2006 8:03:33 PMAPASS
CALL DON TO SCHEDULE; Phone #: ###-#### Internet Inspection Request from: Allison Briggs..discussed some issues before final..s/f dampers, duct detectors. flex duct, etc
MEC06-02177 Conference8/28/20068/30/20068/30/2006 8:02:51 PMAPASS
call DON to schedule; Phone #: ###-#### Internet Inspection Request from: Allison Briggs..discussed some issues before final..s/f dampers, duct detectors, flex duct, etc
MEC06-01849 Conference8/28/20068/30/20068/30/2006 8:02:03 PMAPASS
CALL DON TO SCHEDULE; Phone #: ###-#### Internet Inspection Request from: Allison Briggs..discussed some issues before the final...s/f dampers, duct detectors, flex duct, etc
MEC06-02732 Final8/29/20068/30/20068/30/2006 4:00:27 PMAFAIL
shawn; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles..need combustion air
MEC06-02381 Final8/30/20068/30/20068/30/2006 3:35:35 PMPNR
randall; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles...waiting for heating contractor
MEC06-02122 Final8/29/20068/30/20068/30/2006 2:08:07 PMAPASS
###-#### don
MEC06-02736 Conference8/30/20068/30/20068/30/2006 1:46:00 PMPPASS
please do pressure witness also; Phone #: ###-#### Internet Inspection Request from: Becky Sucher
MEC06-02742 Conference8/29/20068/30/20068/30/2006 11:07:58 AMAPASS
meet jd at 10:30
MEC06-02704 Rough-in8/29/20068/30/20068/30/2006 9:17:28 AMAPASS
shelley ###-####
MEC06-02511 Rough-in8/29/20068/30/20068/30/2006 9:17:13 AMAPASS
Phone #: ###-#### Internet Inspection Request from: APRIL THOMAS