BLD17-04447
| FIRE-Conference | 8/30/2019 | 8/30/2019 | 8/30/2019 3:24:53 PM | P | DONE |
|
|
Jim and I discussed the smoke detectors for the daycare area of this project. See E3.1 drawing sheet for reference.
|
FIR19-00612
| INSP-Final Inspection | 8/29/2019 | 8/30/2019 | 8/30/2019 2:19:20 PM | P | FAIL |
|
|
Contractor needs to finish wiring the trouble output from the communicator to the FACP and then test.
|
FIR18-00525
| INSP-Sprinkler Rough-in | 8/29/2019 | 8/30/2019 | 8/30/2019 12:59:18 PM | A | PASS |
|
|
Rough-in is for the west area and clouds passed. Piping can be covered.. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR15-00520
| INSP-Final Inspection | 8/30/2019 | 8/30/2019 | 8/30/2019 12:58:28 PM | P | PASS |
|
|
Permit finaled by Jim.
Jim, this project was finaled and I emailed the Record of Completion over too you. Eric from my office said I needed to change the inspection type in the portal so you can sign it off. Brent Crane Inspection requested via web by Fire Scheduler
|
FIR19-00618
| INSP-Final Inspection | 8/30/2019 | 8/30/2019 | 8/30/2019 12:24:47 PM | P | PASS |
|
|
Permit finaled.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
BLD19-02650
| FIRE-Final Inspection | 8/29/2019 | 8/30/2019 | 8/30/2019 10:33:57 AM | A | FAIL |
|
|
No city approved documents on site. I did perform a courtesy inspection of typical life safety items. Maureen Phone #: ###-####
|
BLD18-00103
| FIRE-Final Inspection | 8/29/2019 | 8/30/2019 | 8/30/2019 10:07:39 AM | P | PASS |
|
|
Life safety passed. Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD18-00104
| FIRE-Final Inspection | 8/29/2019 | 8/30/2019 | 8/30/2019 10:07:18 AM | A | PASS |
|
|
Life safety passed. Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD19-01687
| FIRE-Final Inspection | 8/29/2019 | 8/30/2019 | 8/30/2019 10:06:17 AM | A | FAIL |
|
|
Contacted an associate at the store who contacted the store manager, Ben, who does not have any city approved documents. No inspection performed. I left message of situation on this contacts voice mail.
Store mngr has approved set of drawings, and permits. Mngr is also aware of the scheduled inspection, and alarm tests. Any questions please feel free to contact me. Phone #: ###-#### Inspection requested via web by Clifford Butler
|
FIR19-00374
| INSP-Sprinkler Rough-in/Hydro | 8/29/2019 | 8/30/2019 | 8/30/2019 9:43:38 AM | A | PASS |
|
|
Hydro for the relo cated FDC witnesseed. Tenting repaired in the two third floor apartments on the east side of the center breezeway.. Gabe Garduno is the contact. This is for a FDC Hydro. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
BLD19-03132
| FIRE-Final Inspection | 8/23/2019 | 8/30/2019 | 8/30/2019 9:11:27 AM | A | FAIL |
|
|
Left message on contacts voice mail. Went to office but doors are locked. No contact made. No inspection performed.
Johnathon Phone #: ###-####-can you please call 30 minutes pirior to meet for access
|
FIR19-00461
| INSP-Final Inspection | 8/29/2019 | 8/30/2019 | 8/30/2019 8:42:26 AM | A | FAIL |
|
|
FIre smoke damper did not function when smoke detector activated. Both dampers will need to be tested. Per Boise Fire a temp for fire alarm will be ok, when dampers function, until the fire alarm upgrade agreement is finalized. Phone #: ###-#### Inspection requested via web by Kristin Dolan
|
BLD19-02506
| FIRE-Final Inspection | 8/29/2019 | 8/30/2019 | 8/30/2019 8:40:37 AM | A | PASS |
|
|
Life safety passed. Card signed. MATT Phone #: ###-####
|