BLD00-01133
| FIRE-Sprinkler Rough-in | 8/3/2000 | 8/4/2000 | 8/4/2000 12:00:00 AM | A | PART |
|
|
###-#### Ok on sprinkler R/I of existing sales area 8/7/00 8:38:22 AM
|
BLD99-01399
| FIRE-Sprinkler Rough-in | 8/3/2000 | 8/4/2000 | 8/4/2000 12:00:00 AM | A | PART |
|
|
robert--###-#### fire life safety insp Final ok on corridor #1 8/7/00 8:55:51 AM
|
BLD00-00080
| FIRE-Final Inspection | 8/3/2000 | 8/4/2000 | 8/4/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 08/03/2000 at 17:18:54. Contact: ###-####. Reinsp. ok for perm. occ. 8/7/00 8:38:06 AM
|
BLD00-00830
| BLD-Final | 8/4/2000 | 8/4/2000 | 8/4/2000 12:00:00 AM | A | PASS |
|
|
Reinsp. ok for temp. occ.
|
FIR00-00216
| INSP-Supply line flush | 8/4/2000 | 8/4/2000 | 8/4/2000 12:00:00 AM | P | PART |
|
|
Tyson; ###-#### Ok supply line flush 8/7/00 8:39:49 AM
|
FIR00-00216
| INSP-Sprinkler Rough-in/Hydro | 8/4/2000 | 8/4/2000 | 8/4/2000 12:00:00 AM | P | PART |
|
|
Tyson; ###-#### Ok above ground hydro test 8/7/00 8:39:58 AM
|