FIR03-00816
| INSP-Sprinkler Rough-in/Hydro | 8/3/2004 | 8/4/2004 | 8/4/2004 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 8/3/2004 at 7:47:57 AM. Contact: ###-####. The 6 inch main from riser to bldg A has been completed - bldg A has charged system; will test flows/tamper on 8/5; UG requires hydro or provide proof it has been completed; all pipe/riser in bldg B will need hydro 8/4/2004 3:22:15 PM 8/4/2004 3:23:15 PM
|
FIR04-00428
| INSP-Sprinkler Rough-in/Hydro | 8/4/2004 | 8/4/2004 | 8/4/2004 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 8/4/2004 at 9:19:09 AM. Requirements of 4 or less heads on one inch and no more than 6 from the 1.25 inch is met; okay to cover third floor only 8/4/2004 2:35:41 PM
|
FIR03-00343
| INSP-Final Inspection | 8/3/2004 | 8/4/2004 | 8/3/2004 4:27:45 PM | P | CANC |
|
|
contact: Terry, Idaho State Fire Marshall will be out at 2:30; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|