FIR08-00255
| INSP-Final Inspection | 7/31/2008 | 8/4/2008 | 8/4/2008 4:56:05 PM | A | PART |
|
|
See red-lines on plans for locations of initiation devices tested today and areas in need of adjustment.
|
FIR07-00606
| INSP-Sprinkler Rough-in/Hydro | 8/4/2008 | 8/4/2008 | 8/4/2008 4:52:27 PM | P | PART |
|
|
Completed forward flow testing, noted some items repaired including proper head temps at skylights in the library, added head at the riser room, storage room area separation has been installed, spacing adjusted where needed, tampers and flow switches tested. Still need as-built plans as requested, area A correction items are not finished.
|
FIR08-00202
| INSP-Final Inspection | 8/4/2008 | 8/4/2008 | 8/4/2008 2:50:47 PM | A | PASS |
|
|
Field inspection passed per scope of work, fire sprinkler permit finaled.
|
BLD08-01459
| FIRE-Conference | 8/4/2008 | 8/4/2008 | 8/4/2008 2:02:48 PM | P | DONE |
|
|
Conference completed regarding hardware at doors to the outdoor terrace, fire extinguisher requirements, backup generator power source for the existing exit signs.
|
FIR08-00463
| INSP-Sprinkler Rough-in/Hydro | 8/4/2008 | 8/4/2008 | 8/4/2008 1:58:56 PM | A | PART |
|
|
Upright sprinkler protection for the shell only has been verified.
|
FIR08-00117
| INSP-Final Inspection | 8/4/2008 | 8/4/2008 | 8/4/2008 1:46:25 PM | A | PASS |
|
|
Fire sprinkler permit finaled.
|
FIR08-00281
| INSP-Sprinkler Rough-in/Hydro | 8/1/2008 | 8/4/2008 | 8/4/2008 1:45:42 PM | A | NR |
|
|
UG hydrostatic test not yet ready for inspection.
|
FIR08-00281
| INSP-Supply line flush | 8/1/2008 | 8/4/2008 | 8/4/2008 1:43:57 PM | A | PART |
|
|
UG fire supply line and remote FDC piping flush completed satisfactory.
|