Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR04-00634 INSP-Conference7/27/20108/4/20108/11/2010 11:38:18 AMADONE
Follow up conference with Keith (head of maintenance), on site, for project status and he stated that ADT would be contacting me.
BLD10-01192 FIRE-Final Inspection8/4/20108/4/20108/4/2010 3:55:23 PMPPASS
Life safety passed.
FIR10-00238 INSP-Sprinkler Rough-in/Hydro8/4/20108/4/20108/4/2010 3:08:56 PMPPASS
The overhead hydro tests of both systems passed.
BLD10-01192 FIRE-Alarm Testing8/4/20108/4/20108/4/2010 3:03:40 PMPPASS
Remote stations installed and duct detector testing passed.
FIR10-00307 INSP-Final Inspection8/4/20108/4/20108/4/2010 2:26:56 PMPFAIL
The trouble signal from the fm200 panel was received at the facp as a supervisory. After that was changed we found that the signals were not being received correctly at the monitoring station. I stayed as long as possible but corrections could not be completed. Will need to be rescheduled.
BLD10-00780 FIRE-Alarm Testing8/4/20108/4/20108/4/2010 2:25:08 PMPCANC
The project related fire alarm and fm200 system permits are not finaled yet.
BLD10-00780 FIRE-Final Inspection8/4/20108/4/20108/4/2010 2:24:44 PMPCANC
The project related fire alarm and fm200 system permits are not finaled yet.
FIR10-00321 INSP-Sprinkler Rough-in8/3/20108/4/20108/4/2010 2:23:51 PMPPASS
All of the sprinkler piping is complete and can be covered except for the 1 1/4" main has not been installed or the new pendant head in front of the doorway.
FIR10-00262 INSP-Sprinkler Rough-in/Hydro8/4/20108/4/20108/4/2010 1:03:30 PMPPASS
The overhead hydro test passed.
BLD10-00114 FIRE-Conference8/4/20108/4/20108/4/2010 11:32:27 AMADONE
Talked about relocation of planned exposed fire sprinkler lines in order to have them concealed. These changes need to be submitted to tim frost for approval. Also we discussed the combustible concealed space. There are two basic options which are fill the space entirely with non-combustible insulation or provide sprinkler protection. Also the fire sprinkler riser needs to be relocated out of the access door way to the riser room.
MIS10-00226 FIR-Conference7/30/20108/4/2010 A 
follow up inspection