Inspections for the day of: Thursday, August 4, 2011.
Number of inspections: 18
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD11-01379 FIRE-Final Inspection8/4/20118/4/20118/4/2011 4:43:27 PMPCANC
Canceled due to inspection load. I requested for the contractor to reschedule.
BLD11-00028 FIRE-Final Inspection8/4/20118/4/20118/4/2011 4:43:03 PMPCANC
Canceled due to inspection load. I requested for the contractor to reschedule.
FIR11-00384 INSP-Final Inspection8/4/20118/4/20118/4/2011 4:42:15 PMPCANC
Canceled due to inspection load. I requested for the contractor to reschedule.
FIR11-00311 INSP-Sprinkler Rough-in8/4/20118/4/20118/4/2011 3:56:23 PMPCANC
Cancelled due to inspection load. Jeff said he would call it back in for tomorrow.
BLD11-01089 FIRE-Final Inspection8/3/20118/4/20118/4/2011 3:52:25 PMPPASS
life safety passed
FIR11-00322 INSP-Final Inspection8/4/20118/4/20118/4/2011 3:42:46 PMPPASS
Permit finaled
FIR11-00221 INSP-Sprinkler Rough-in8/4/20118/4/20118/4/2011 3:41:26 PMPPASS
The underground piping is ok to cover.
FIR11-00039 INSP-Final Inspection8/3/20118/4/20118/4/2011 2:17:39 PMPFAIL
Started the fire alarm testing by verifying the fire sprinkler interconnections. When we called the monitoring company I found that no supervisory signals had been received. It appears that account is not set up for these. No further testing was done. Separate phone lines have been verified. Forrest's redline comments have not been verified.
FIR11-00038 INSP-Final Inspection8/3/20118/4/20118/4/2011 2:17:16 PMPFAIL
Started the fire alarm testing by verifying the fire sprinkler interconnections. When we called the monitoring company I found that no supervisory signals had been received. It appears that account is not set up for these. No further testing was done. Separate phone lines have been verified. Forrest's redline comments have not been verified.
FIR10-00583 INSP-Final Inspection8/3/20118/4/20118/4/2011 2:14:51 PMPPASS
Permit finaled
FIR11-00330 INSP-Sprinkler Rough-in8/4/20118/4/20118/4/2011 11:47:29 AMPPASS
Todays inspection was only for the attic sprinkler head lines. The rough-in on these were fine except Rick had to adjust the vertical elevation while I waited. I also posted a stop work order and a parcel hold due to the installation of sheet rock prior to approval and the installation of the sprinkler system at the west end of the building.
BLD10-02865 BLD-Other8/4/20118/4/20118/4/2011 11:44:59 AMPDONE
A stop work order is being issued by Troy Cobbley due to sheet rock being installed without approval and prior to portions of the sprinkler system being installed. Notices were posted on site. The building contractor was not on site to discuss the situation.
FIR08-00239 INSP-Sprinkler Rough-in8/3/20118/4/20118/4/2011 11:42:43 AMAPASS
See the city approved plans for my initials and todays date for apartments where the piping to the sprinkler drops can be covered and at the garbage shutes where the piping can be covered.
BLD11-00859 FIRE-Final Inspection8/3/20118/4/20118/4/2011 10:44:55 AMAFAIL
Provide exit discharge lighting at both of the exits as per the approved plans, mount and tag the fire extinguishers as discussed, provide single action hardware on the new ADA restroom door. Per Tim and Jason the round door knobs on the arcade booths can remain.
BLD11-01211 FIRE-Final Inspection8/2/20118/4/20118/4/2011 9:50:53 AMAPASS
life safety passed.
FIR11-00323 INSP-Final Inspection8/4/20118/4/20118/4/2011 9:49:51 AMPPASS
permit finaled
FIR11-00374 INSP-Sprinkler Rough-in8/3/20118/4/20118/4/2011 9:47:26 AMAPASS
The underground supply piping is ok to cover. The installation of the tie in to the United water tap does not match plan and the fire aprinkler contractor decided not to install the PIV but to install a wall PIV. This change is to be shown on the overhead pipng submittals.
BLD11-01162 FIRE-Final Inspection8/3/20118/4/20118/4/2011 6:22:24 AMAPASS
life safety passed