BLD13-02425
| FIRE-Final Inspection | 8/4/2015 | 8/4/2015 | 8/4/2015 4:13:57 PM | P | PASS |
|
|
Fire life safety inspection of new apartment building, including test of exit signs and emergency lighting units throughout the building. Several EM lights need to be repaired/replaced. Also need additionl exit signs in south corridor (all floors) to clearly indicate the direction of egress to the southeast exit stair. EVAC plans need to be installed. Fire Exting. OK ****AS PER sja FINAL PASSED****
|
FIR14-00898
| INSP-Final Inspection | 8/4/2015 | 8/4/2015 | 8/4/2015 4:07:37 PM | P | PART |
|
|
Completion of fire alarm system testing, including test os all HVAC shutdown SDS that were not operating last visit. Tested DP valves in PG, however one system (north side) did not operate correctly. Tested all notification devices in garage that were missing at last inspection. Fire alarm system testing completed, except for fire sprinklers that need to be completed and retested.
|
FIR14-00603
| INSP-Sprinkler Rough-in | 8/3/2015 | 8/4/2015 | 8/4/2015 4:03:49 PM | A | FAIL |
|
|
Trip test of dry pipe systems protecting the parng garage. The south system tested OK, wheras the north system did not meet 60 seconds trip test. Suspected some blockage within system. Will retest after the problem is addressed.
|
FIR14-00687
| INSP-Sprinkler Rough-in/Hydro | 8/4/2015 | 8/4/2015 | 8/4/2015 4:00:57 PM | P | PART |
|
|
RTC inspection for west dry system in parking garage. Need to add 4 DP heads in south west corner. Otherwise OK to cover the pipe for this system.
|
FIR15-00096
| INSP-Sprinkler Rough-in | 8/4/2015 | 8/4/2015 | 8/4/2015 3:55:29 PM | P | PART |
|
|
RTC inspection for 3rd floor corridors (all sides), including elevator lobbies. Need to add (1) A/S in center lobby, near east hallway. Otherwise OK to cover 3rd floor corridor pipe. Also inspected 2nd floor elevator lobbies - center and south sides. OK to cover the pipe in these areas.
|
FIR14-00815
| INSP-Final Inspection | 8/3/2015 | 8/4/2015 | 8/4/2015 12:39:20 PM | A | PART |
|
|
Final inspection of corridors and residential units for floors 2 and 3. 4th floor not ready for insection this visit.
|
FIR14-00815
| INSP-Sprinkler Rough-in | 8/3/2015 | 8/4/2015 | 8/4/2015 12:36:14 PM | A | PASS |
|
|
This is a dry system trip for 4/1 north.
|
FIR14-00708
| INSP-Sprinkler Rough-in | 8/3/2015 | 8/4/2015 | 8/4/2015 12:23:23 PM | A | PART |
|
|
RTC inspection for hard lids in Bldg G- 1st, 2nd, 3rd floors. See plans for areas inspected today. OK to cover these areas.
|
FIR14-00792
| INSP-Sprinkler Rough-in | 8/3/2015 | 8/4/2015 | 8/4/2015 12:21:23 PM | A | PART |
|
|
RTC inspection for hard lid areas for the 2nd floor - Bldg H. See plans for areas inspected. OK to cover piping inspected today.
|
FIR14-00815
| INSP-Final Inspection | 8/3/2015 | 8/4/2015 | 8/3/2015 2:18:55 PM | P | CANC |
|
|
Final inspections pending completion of dry pipe valve trip testing. Final walkthroughs inspections will be conducted only after all painting is completed. Some stairwells still be ing painted.
|