FIR20-00380
| INSP-Final Inspection | 7/28/2020 | 8/4/2020 | 8/4/2020 4:15:55 PM | P | FAIL |
|
|
Fire bell by FDC rang only with flow from the wet system in the fire pump room, bell needs to ring during water flow on all of the other sprinkler systems throughout the building as well. Pull stations exceed 48 inches off of finish floor. PIV tamper could not be tested on the northwest side of building, PIV handle is seized and would not turn. Demo old NAC panel that is no longer in service. Tamper valve on hose valves from riser 5 needs to be connected per IFC 903.4. Provide conduit connector for riser 5 OS&Y tamper as discussed. Tamper switch on riser 6 would not stay clear, was determined that switch will need to be replaced. Other than items noted fire sprinkler monitoring is complete.
Crane Alarm and sprinkler contractor will be on site at 12:00PM Phone #: ###-#### Inspection requested via web by Fire Scheduler
|
BLD20-00796
| FIRE-Conference | 8/3/2020 | 8/4/2020 | 8/4/2020 4:07:36 PM | A | DONE |
|
|
Fire conference is complete.
Curtis *screened* Phone #: ###-####
|
FIR20-00013
| INSP-Final Inspection | 7/29/2020 | 8/4/2020 | 8/4/2020 3:50:27 PM | P | PASS |
|
|
Final inspection for scope of work is complete.
Please call 20-30 minutes prior to inspection. You will be meeting technician Justin Volquarden on site. Phone #: ###-#### Inspection requested via web by jason petty
|
FIR20-00014
| INSP-Final Inspection | 7/29/2020 | 8/4/2020 | 8/4/2020 3:50:08 PM | P | PASS |
|
|
Final inspection for scope of work is complete.
Please call 20-30 minutes prior to inspection. You will be meeting technician Justin Volquardsen on site. Phone #: ###-#### Inspection requested via web by jason petty
|
FIR20-00015
| INSP-Final Inspection | 7/29/2020 | 8/4/2020 | 8/4/2020 3:49:40 PM | P | PASS |
|
|
Final inspection for scope of work is complete.
Please call 20-30 minutes prior to inspection. You will be meeting technician Justin Volquardsen on site. Phone #: ###-#### Inspection requested via web by jason petty
|
BLD20-00330
| FIRE-Final Inspection | 8/3/2020 | 8/4/2020 | 8/4/2020 9:46:01 AM | A | PASS |
|
|
Previously noted items have been corrected, no fire sprinklers, no fire alarms, duct detectors are stand-alone and functional with annuciators, fire extingiushers are placed with current inspection tags. Final life fire safety inspection complete, signature card not available at time of inspection.
Sean *screened* Phone #: ###-####
|
BLD20-02241
| FIRE-Final Inspection | 8/3/2020 | 8/4/2020 | 8/4/2020 8:25:06 AM | A | PASS |
|
|
No fire sprinkler modifications, no fire alarm modifications, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection is complete, signatures provided on permit sign off card.
Screened- Reza Phone #: ###-####
|
FIR20-00135
| INSP-Final Inspection | 8/3/2020 | 8/4/2020 | 8/4/2020 8:20:28 AM | A | CANC |
|
|
screened // Jonathan Phone #: ###-#### Inspection cancelled from web by: Jonathan Lee
|
FIR20-00133
| INSP-Final Inspection | 8/3/2020 | 8/4/2020 | 8/4/2020 8:20:24 AM | A | CANC |
|
|
screened // Jonathan Phone #: ###-#### Inspection cancelled from web by: Jonathan Lee
|
FIR20-00130
| INSP-Final Inspection | 8/3/2020 | 8/4/2020 | 8/4/2020 8:20:20 AM | A | CANC |
|
|
screened // Jonathan Phone #: ###-#### Inspection cancelled from web by: Jonathan Lee
|
FIR20-00129
| INSP-Final Inspection | 8/3/2020 | 8/4/2020 | 8/4/2020 8:20:16 AM | A | CANC |
|
|
screened // Jonathan Phone #: ###-#### Inspection cancelled from web by: Jonathan Lee
|
FIR20-00121
| INSP-Final Inspection | 8/3/2020 | 8/4/2020 | 8/4/2020 8:20:13 AM | A | CANC |
|
|
screened // Jonathan Phone #: ###-#### Inspection cancelled from web by: Jonathan Lee
|
BLD20-01684
| FIRE-Final Inspection | 8/3/2020 | 8/4/2020 | 8/4/2020 8:11:13 AM | A | FAIL |
|
|
Fire alarm notification required in changing room, a seperate permit is required for all fire alarm modifications. Provide annual inspection for fire extingiusher. Provide suite number for tenant space.
Nicole Phone #: ###-####
|
FIR20-00490
| INSP-Final Inspection | 8/3/2020 | 8/4/2020 | 8/4/2020 8:08:59 AM | A | PASS |
|
|
Final fire sprinkler inspection for scope of work is complete.
Thank you have a good day Phone #: ###-#### Inspection requested via web by jeremiah robison
|