BLD19-01303
| BLD-Aging Inspection | 8/4/2020 | 8/4/2020 | 8/5/2020 8:28:45 AM | | PEND |
|
|
|
BLD19-03516
| BLD-Aging Inspection | 8/4/2020 | 8/4/2020 | 8/5/2020 8:28:03 AM | | PEND |
|
|
|
BLD20-01768
| BLD-Foundation | 8/4/2020 | 8/4/2020 | 8/4/2020 4:51:04 PM | P | PASS |
|
|
|
BLD20-01731
| BLD-Foundation | 8/4/2020 | 8/4/2020 | 8/4/2020 4:50:47 PM | P | PASS |
|
|
|
BLD20-00337
| BLD-Foundation | 8/4/2020 | 8/4/2020 | 8/4/2020 4:49:26 PM | P | DEFR |
|
|
*Screened* masonary & foundation - Chase Phone #: ###-####//defer to special inspections//
|
BLD20-02049
| BLD-Foundation | 8/4/2020 | 8/4/2020 | 8/4/2020 3:36:20 PM | P | PASS |
|
|
*Screened* monolythic pour - Ryan Phone #: ###-####//per plans//advised to add ufer ground for electrical//
|
BLD20-02013
| BLD-Framing/Rough-in | 8/4/2020 | 8/4/2020 | 8/4/2020 3:35:26 PM | P | FAIL |
|
|
Framing and sheer inspection. Phone #: ###-#### Inspection requested via web by sergio molina//shear only as trades rough ins are not complete or inspected//need to add hot dip galvanized nails at pressure treated plates//need to block all panel breaks at shear locations//add anchor bolts//CN left with permit paper work near washer box//
|
BLD20-01341
| BLD-Framing/Rough-in | 8/4/2020 | 8/4/2020 | 8/4/2020 3:11:36 PM | P | PASS |
|
|
truss repair document reviewed//putty pad added to recepticles per the super, fire cualk was used at wall penetrations//ok to cover//
|
BLD20-01340
| BLD-Framing/Rough-in | 8/4/2020 | 8/4/2020 | 8/4/2020 3:11:14 PM | P | PASS |
|
|
truss repair document reviewed//putty pad added to recepticles per the super, fire cualk was used at wall penetrations//ok to cover//
|
BLD20-01339
| BLD-Framing/Rough-in | 8/4/2020 | 8/4/2020 | 8/4/2020 3:10:18 PM | P | PASS |
|
|
truss repair document reviewed//putty pad added to recepticles per the super, fire cualk was used at wall penetrations//ok to cover//
|
BLD20-01279
| BLD-Framing/Rough-in | 8/4/2020 | 8/4/2020 | 8/4/2020 3:09:54 PM | P | PASS |
|
|
truss repair document reviewed//putty pad added to recepticles per the super, fire cualk was used at wall penetrations//ok to cover//
|
BLD20-01361
| BLD-Framing/Rough-in | 8/3/2020 | 8/4/2020 | 8/4/2020 2:23:55 PM | P | PASS |
|
|
This is for framing inspection of both garages, also fire seal of the separation walls on both garage units.
Phone #: ###-#### Inspection requested via web by Joel Hirtletruss repair document reviewed//putty pad added to recepticles per the super, fire cualk was used at wall penetrations//ok to cover//
|
BLD20-01360
| BLD-Framing/Rough-in | 8/4/2020 | 8/4/2020 | 8/4/2020 2:23:38 PM | P | PASS |
|
|
truss repair document reviewed//putty pad added to recepticles per the super, fire cualk was used at wall penetrations//ok to cover//
|
BLD20-01359
| BLD-Framing/Rough-in | 8/4/2020 | 8/4/2020 | 8/4/2020 2:23:19 PM | P | PASS |
|
|
truss repair document reviewed//putty pad added to recepticles per the super, fire cualk was used at wall penetrations//ok to cover//
|
BLD20-01358
| BLD-Framing/Rough-in | 8/4/2020 | 8/4/2020 | 8/4/2020 2:23:00 PM | P | PASS |
|
|
truss repair document reviewed//putty pad added to recepticles per the super, fire cualk was used at wall penetrations//ok to cover//
|
BLD20-01749
| BLD-Framing/Rough-in | 8/4/2020 | 8/4/2020 | 8/4/2020 1:40:13 PM | P | PASS |
|
|
Screened- Erik Phone #: ###-####//fur out wall cover only//ok per plans//
|
BLD20-02606
| BLD-Final | 8/4/2020 | 8/4/2020 | 8/4/2020 1:22:11 PM | P | DONE |
|
|
Inspection on a completed asphalt roofing project. Phone #: ###-#### Inspection requested via web by Michael La Pointe
|
BLD20-02606
| DOC - Permit Finaled | 8/4/2020 | 8/4/2020 | 8/4/2020 1:22:01 PM | P | PASS |
|
|
new roof flashing and vents installed//rolled roofing installed per description//
|
BLD19-04985
| BLD-Footing | 8/4/2020 | 8/4/2020 | 8/4/2020 12:46:05 PM | P | FAIL |
|
|
need small documents and form 310 for special inspections//site plan shows rear setback of 10 feet minimum, current site conditions set at 8'//talked with general contractor, will need to submit for 8' setback or meet minimums on site plan A101//
|
BLD20-01070
| BLD-Footing | 8/3/2020 | 8/4/2020 | 8/4/2020 12:44:31 PM | P | CANC |
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru//wrong permit//
|
BLD19-00538
| BLD-Footing | 8/3/2020 | 8/4/2020 | 8/4/2020 12:06:27 PM | A | PART |
|
|
Footing pour on garage 5. Concrete pour at noon Phone #: ###-#### Inspection requested via web by Travis Blackburn//need to add verts at 18" oc per the plans//special inspector onsite, will verify prior to pour//pend specials approvals//
|
BLD20-00399
| BLD-Framing/Rough-in | 8/4/2020 | 8/4/2020 | 8/4/2020 11:14:25 AM | A | PART |
|
|
structural/bearing Phone #: ###-#### Inspection requested via web by Shane Shade//See Russell for notes on corrections for beams, posts, joists,bearing, anchor bolts, and hold downs//ok to insulate separation walls only at this time//this inspection was not a complete framing inspection//
|
BLD20-00398
| BLD-Framing/Rough-in | 8/4/2020 | 8/4/2020 | 8/4/2020 11:14:10 AM | A | PART |
|
|
structural/bearing Phone #: ###-#### Inspection requested via web by Shane Shade//See Russell for notes on corrections for beams, posts, joists,bearing, anchor bolts, and hold downs//ok to insulate separation walls only at this time//this inspection was not a complete framing inspection//
|
BLD20-00397
| BLD-Framing/Rough-in | 8/4/2020 | 8/4/2020 | 8/4/2020 11:13:56 AM | A | PART |
|
|
Structural/Bearing points Phone #: ###-#### Inspection requested via web by Shane Shade//See Russell for notes on corrections for beams, posts, joists,bearing, anchor bolts, and hold downs//ok to insulate separation walls only at this time//this inspection was not a complete framing inspection//
|
BLD20-00357
| BLD-Framing/Rough-in | 8/4/2020 | 8/4/2020 | 8/4/2020 11:13:41 AM | A | PART |
|
|
Structural/bearing points Phone #: ###-#### Inspection requested via web by Shane Shade//See Russell for notes on corrections for beams, posts, joists,bearing, anchor bolts, and hold downs//ok to insulate separation walls only at this time//this inspection was not a complete framing inspection//
|
BLD20-01191
| BLD-Framing/Rough-in | 8/3/2020 | 8/4/2020 | 8/4/2020 11:12:21 AM | A | PART |
|
|
screened // Chris Phone #: ###-####//work accordig to engineering was completed//engineers letter addressed sistered joists at main floor--they are ok, other areas are existing conditions//trades sign offs ok//corrections made, many areas are existing conditions, code compliance was acheived where possible or areas that are exposed//ok to insulate//
|
BLD19-04500
| BLD-Foundation | 8/3/2020 | 8/4/2020 | 8/4/2020 9:41:20 AM | A | PASS |
|
|
Pat - */Screened*/ Phone #: ###-####
|
BLD20-01563
| BLD-Energy code compliance | 8/3/2020 | 8/4/2020 | 8/4/2020 9:15:34 AM | A | PASS |
|
|
screened // Christina Phone #: ###-####//.30 windows//R21 walls//ok to cover//
|
BLD19-03701
| BLD-Final | 8/3/2020 | 8/4/2020 | 8/4/2020 8:57:44 AM | A | FAIL |
|
|
Mark *no one on site, call for access* Screened* Phone #: ###-####//correction notice posted for three corrections that were not completed for code compliance//
|
BLD19-03701
| BLD-Blower Door Test Results | 8/4/2020 | 8/4/2020 | 8/4/2020 8:56:51 AM | A | DONE |
|
|
3.8 ACH 50
|
MIS20-00242
| BLD-Conference | 8/3/2020 | 8/4/2020 | 8/4/2020 8:28:38 AM | A | DONE |
|
|
possible roof work without permit//correction notice left with worker onsite, spoke to supervisor on phone, should be getting a permit pulled for the work//follow up 5 days/
|