FIR09-00033
| INSP-Sprinkler Rough-in/Hydro | 8/4/2009 | 8/5/2009 | 8/5/2009 6:27:29 PM | P | PART |
|
|
OH rough-in for systems 11 and 13 completed today-see plans for changes to be made at the electrical room system 13.
|
FIR09-00290
| INSP-Final Inspection | 8/4/2009 | 8/5/2009 | 8/5/2009 6:26:04 PM | A | FAIL |
|
|
HVAC unit 28 is not functional at the dry goods area. Main office area items include three notification devices to be relocated due to overspacing or obstruction-see plan annotations, smoke detector at the UPS room needs relocated away from the HVAC diffuser, adjust cd at the womens locker a/v, added MP at the east exit is not shown on plans, provide a WP strobe at the mens showers, duct detectors are not functioning correctly, several mag locks are not powered or interconnected at this time, need to verify locker height which may obstruct coverage, notification not tested due to pending changes. Items retested okay include heat detector at the electrical room, notification at the printer room, and DD address 26. Rack system in the dry goods section is not finished for FS and TS testing.
|
FIR09-00033
| INSP-Sprinkler Rough-in/Hydro | 7/29/2009 | 8/5/2009 | 8/5/2009 6:14:39 PM | A | PART |
|
|
Overhead hydrostatic testing for systems 31, 23,24,17 not including 4" rack system, 25,riser room#3, riser room#4, and 18 not including the 4" rack system passed.
|
FIR09-00283
| FIR-Aging Inspection | 8/5/2009 | 8/5/2009 | 8/5/2009 6:10:51 PM | | DONE |
|
|
Work in progress
|
FIR09-00464
| INSP-Sprinkler Rough-in | 8/4/2009 | 8/5/2009 | 8/5/2009 6:09:59 PM | A | PART |
|
|
Overhead fire sprinkler system modifications per the scope of work are okay for cover at the drop ceilings.
|