Inspections for the day of: Wednesday, August 5, 2009.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorClint A Smith
TitleEROSION CONTROL INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC09-00458 General Inspection8/5/20098/5/20098/6/2009 11:56:12 AMPPASS
ESC09-00484 Site Preparation8/5/20098/5/20098/5/2009 3:08:25 PM PASS
ESC09-00483 Site Preparation8/5/20098/5/20098/5/2009 2:48:59 PM PASS
ESC08-00821 DOC - Permit Finaled8/5/20098/5/20098/5/2009 2:13:02 PMPPASS
ESC08-00952 Tracking Control8/5/20098/5/20098/5/2009 1:44:47 PMPFAIL
Correction Notice: (Message to RP)
1. Install a stabilized Construction Exit or block off access at the south west end of project area.
2. Clean up all sediment and debris off of all hard surfaces at the south west end of project area.
3. Protect storm drain inlets with the residental neighborhood from the south west end of project area.
Failure to comply with correction notice within the given time frame will result in a Stop Work Order.

Will re-inspect on 8/6/09 AM.
ESC08-00952 Complaint Inspection8/5/20098/5/20098/5/2009 1:42:44 PMPFAIL
Correction Notice: (Message to RP)
1. Install a stabilized Construction Exit or block off access at the south west end of project area.
2. Clean up all sediment and debris off of all hard surfaces at the south west end of project area.
3. Protect storm drain inlets with the residental neighborhood from the south west end of project area.
Failure to comply with correction notice within the given time frame will result in a Stop Work Order.

Will re-inspect on 8/6/09 AM.
ESC08-00491 Random Inspection8/5/20098/5/20098/5/2009 10:04:30 AMAPART
Still workoing on the issue stated within the previous inspection. Will re-inspect on 7/6/09AM
ESC08-00657 Site Preparation8/5/20098/5/20098/5/2009 9:30:40 AM NR
Will re-inspect in 2 weeks.
ESC09-00259 Site Preparation8/5/20098/5/20098/5/2009 9:19:55 AM NR
ESC09-00357 Site Preparation8/5/20098/5/20098/5/2009 9:07:12 AM CANC
Duplicate.
ESC09-00357 Site Preparation8/3/20098/5/20098/5/2009 9:06:29 AMAPASS
Went over with project super and the RP that will be changed over today.
1. The general provisions of what we as a city will be looking for and what we required.