MIS14-00168
| BLD-Conference | 7/29/2014 | 8/5/2014 | 8/6/2014 1:18:47 PM | A | CANC |
|
|
mike.....
|
BLD14-01357
| BLD-Ceiling Grid Inspection | 8/4/2014 | 8/5/2014 | 8/6/2014 7:53:36 AM | P | PASS |
|
|
Curt Phone #: ###-####-please call prior to meet
|
BLD14-01303
| BLD-Footing | 8/5/2014 | 8/5/2014 | 8/6/2014 7:52:43 AM | P | PART |
|
|
Rebar/please call 30min for access - Chris Phone #: ###-#### OK pending MTI special inspections, tests and approvals.
|
BLD13-02595
| BLD-Conference | 8/5/2014 | 8/5/2014 | 8/5/2014 2:45:42 PM | P | DONE |
|
|
Received TCO sign off from zoning/landscape. Looking for structural TCO. Hired new sider. Hired new landscaper. Roofer working and awaiting upper siding. Phone #: ###-#### Inspection requested via web by Brandon Juarez
|
BLD14-00828
| BLD-Final | 8/5/2014 | 8/5/2014 | 8/5/2014 2:45:05 PM | P | PASS |
|
|
david-###-####
|
BLD14-00828
| DOC - Permit Finaled | 8/5/2014 | 8/5/2014 | 8/5/2014 2:44:49 PM | P | PASS |
|
|
|
BLD13-02595
| BLD-Final | 8/5/2014 | 8/5/2014 | 8/5/2014 2:44:27 PM | P | PART |
|
|
OK for Temp Occ. OK for Perm Occ. when Roofing, Siding, is done. Fire, and zoning is finaled.
|
BLD13-02653
| BLD - Resubmittal Approved | 8/5/2014 | 8/5/2014 | 8/5/2014 2:38:27 PM | P | PASS |
|
|
Requesting 60 day extension for sign location. Inspection requested via web by Brandon Juarez
|
BLD14-01586
| BLD-Framing/Rough-in | 8/4/2014 | 8/5/2014 | 8/5/2014 1:31:06 PM | P | NR |
|
|
Brett Phone #: ###-#### Need all rough ins......
|
BLD14-01928
| BLD-Framing/Rough-in | 8/4/2014 | 8/5/2014 | 8/5/2014 1:13:07 PM | A | PART |
|
|
Please call ahead for access - Todd Phone #: ###-#### Super structure Appears OK.... Still adding girts to side walls
|
GCB14-00104
| GCB-Fndatn/slab ins/fld vent | 8/4/2014 | 8/5/2014 | 8/5/2014 12:31:00 PM | A | PASS |
|
|
Raina ###-#### please call to meet onsite for block and tie inspection
|