ELE12-01319
| ELE-Aging Inspection | 8/5/2014 | 8/5/2014 | 8/6/2014 11:17:51 AM | | DONE |
|
|
too busy
|
GCE14-00090
| GCE-Final | 8/5/2014 | 8/5/2014 | 8/5/2014 3:56:20 PM | P | PASS |
|
|
Terry ###-#### corrections made final ok
|
GCE14-00109
| GCE-Final | 8/5/2014 | 8/5/2014 | 8/5/2014 3:40:57 PM | P | PASS |
|
|
Vern ###-#### please call to meet on-site final ok
|
ELE14-01385
| Conference | 8/5/2014 | 8/5/2014 | 8/5/2014 3:04:22 PM | P | DONE |
|
|
Look at existing in slab raceways prior contractor installed. We are contracted to take over scope of work. Phone #: ###-#### Inspection requested via web by Tom Betty contractor to refeed u.ground conduits to n.east sewer ejection pump pits due to inadequate depth of previosly installed conduits
|
ELE14-00250
| Final | 8/5/2014 | 8/5/2014 | 8/5/2014 1:47:20 PM | P | PASS |
|
|
Josh is contact. Thank u Phone #: ###-#### Inspection requested via web by Chris Chesnut final ok
|
ELE14-02107
| Conference | 8/5/2014 | 8/5/2014 | 8/5/2014 1:40:56 PM | P | DONE |
|
|
Kevin-please call prior to getting to job site so he can meet Phone #: ###-#### discuss grounding electrode system for solar install
|
ELE14-01401
| Final | 8/5/2014 | 8/5/2014 | 8/5/2014 12:33:09 PM | P | PASS |
|
|
Robert Phone #: ###-#### Inspection requested via web by Sean DeLacy ESPN Potato Bowl final ok
|
ELE14-02103
| Electrical Rough-In | 8/5/2014 | 8/5/2014 | 8/5/2014 12:04:58 PM | P | PASS |
|
|
Wall Cover. 2nd floor. Danny is the contact Phone #: ###-#### Inspection requested via web by Buster Bowen r/i ok walls
|
ELE14-01071
| Electrical Rough-In | 8/4/2014 | 8/5/2014 | 8/5/2014 10:42:07 AM | A | CANC |
|
|
Contact: Mike Butticci... final on phase #2 portion, 2nd floor Phone #: ###-#### Inspection requested via web by Deb Gooden needed final
|
ELE14-01071
| Final | 8/5/2014 | 8/5/2014 | 8/5/2014 10:41:41 AM | P | PASS |
|
|
Contact: Mike Butticci... final on phase #2 portion, 2nd floor Phone #: ###-#### Inspection requested via web by Deb Gooden final ok phase 2 an 3 on 2nd floor only
|
ELE14-02108
| Electrical Rough-In | 8/5/2014 | 8/5/2014 | 8/5/2014 10:09:51 AM | A | PASS |
|
|
Wall inspection for exterior wall to be covered. Please call to discuss, when on site. Thank You Phone #: ###-#### Inspection requested via web by Eric Brown r/i ok rear exterior wall liv.room
|
ELE14-02034
| Electrical Rough-In | 8/4/2014 | 8/5/2014 | 8/5/2014 9:55:33 AM | A | FAIL |
|
|
Kim Phone #: ###-#### not ready, need nailplates, straping etc
|
ELE14-01427
| Electrical Rough-In | 8/4/2014 | 8/5/2014 | 8/5/2014 9:12:15 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kevin Burke r/i ok
|
ELE14-02127
| Temporary Service | 8/5/2014 | 8/5/2014 | 8/5/2014 8:30:02 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by John VanZandt t/s o/h n ok
|