BLD02-01703
| BLD-Footing | 8/5/2002 | 8/6/2002 | 8/6/2002 12:00:00 AM | A | PASS |
|
|
BRAD; Phone #: ###-####
|
BLD02-01077
| BLD-Framing/Rough-in | 8/5/2002 | 8/6/2002 | 8/6/2002 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 08/05/2002 at 10:56:10. Contact: ###-####. ok for cover area at duct work still needs insp 8/6/2002 9:11:02 AM
|
BLD02-00097
| BLD-Framing/Rough-in | 8/5/2002 | 8/6/2002 | 8/6/2002 12:00:00 AM | A | PART |
|
|
###-#### rex needs all rough ins ok to cover ext walls 8/6/2002 9:29:56 AM
|
BLD02-01497
| BLD-Conference | 8/5/2002 | 8/6/2002 | 8/6/2002 12:00:00 AM | A | PASS |
|
|
bruce borup ###-####, call 1st...minor remodel; contractor didn't call for frame insp prior to cover, would like to meet at site. Elec. & plbg r/i's ok...no hvac performed.
|
BLD02-01497
| BLD-Framing/Rough-in | 8/6/2002 | 8/6/2002 | 8/6/2002 12:00:00 AM | A | PASS |
|
|
|
MEC02-02123
| Final | 8/6/2002 | 8/6/2002 | 8/6/2002 12:00:00 AM | P | NH |
|
|
Scheduled by a contractor via Hello! on 08/06/2002 at 10:27:55. Contact: ###-####.
|
BLD01-02904
| BLD-Final | 8/6/2002 | 8/6/2002 | 8/6/2002 12:00:00 AM | P | PASS |
|
|
###-#### ALLISON iwoiaok 8/6/2002 2:53:57 PM
|
MEC02-02133
| Rough-in | 8/6/2002 | 8/6/2002 | 8/6/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 08/06/2002 at 08:15:05. Contact: ###-####.
|
BLD02-00400
| BLD-Framing/Rough-in | 8/6/2002 | 8/6/2002 | 8/6/2002 12:00:00 AM | P | PART |
|
|
###-#### pete air seal ok check framing corrections at ec insp 8/6/2002 4:00:48 PM
|
MEC02-02019
| Rough-in | 8/6/2002 | 8/6/2002 | 8/6/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 08/06/2002 at 09:34:49. Contact: ###-####.
|
MEC02-01695
| Final | 8/6/2002 | 8/6/2002 | 8/6/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 08/06/2002 at 09:36:05. Contact: ###-####. garage code 8888
|