BLD02-01200
| FIRE-Final Inspection | 8/5/2002 | 8/6/2002 | 8/6/2002 12:00:00 AM | A | PASS |
|
|
Don, ###-####
|
FIR02-00289
| INSP-Sprinkler Rough-in/Hydro | 8/6/2002 | 8/6/2002 | 8/6/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 08/06/2002 at 10:40:47. Contact: ###-####. okay to cover; tenting complete; riser not complete; alarms are supposed to be tied into smoke detectors per Brian; 8/6/2002 3:14:49 PM
|
BLD02-01372
| FIRE-Conference | 8/6/2002 | 8/6/2002 | 8/6/2002 12:00:00 AM | P | PART |
|
|
met with CTA engineers and Carl D.: they are requesting a temp co because the fire alarms won't be complete; told them to contact Dave Miller for temp co 8/6/2002 4:46:25 PM
|
BLD01-03212
| FIRE-Sprinkler Rough-in | 8/6/2002 | 8/6/2002 | 8/6/2002 12:00:00 AM | P | PASS |
|
|
okay to cover
|