Inspections for the day of: Wednesday, August 6, 2003.
Number of inspections: 17
Percentage of inspections complete: 94 %
Percentage of inspections not complete: 6 %
Contact Information
InspectorRick Jackson
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR03-00187 INSP-Alarm Testing7/31/20038/1/2003 A 
###-#### daniel
FIR03-00427 INSP-Final Inspection8/7/20038/6/20038/7/2003 12:00:00 AMPPART
performed inspection from 5-8:30 pm; NAC in basement not sync'd; horn in VIP not temporal; need to verify batteries and voltage drops
FIR03-00225 FIR-Aging Inspection8/6/20038/6/20038/6/2003 12:00:00 AM PASS
the BLD permit and FIR alarm permit aren't ready for final yet; SL construction will need to make sure plans are available at final 8/6/2003 8:06:27 AM
FIR03-00315 INSP-Final Inspection8/5/20038/6/20038/6/2003 12:00:00 AMACANC
Scheduled by a contractor via Hello! on 8/5/2003 at 9:53:09 AM. Contact: ###-####. this permit was called in by mistake by another contractor 8/6/2003 9:52:32 AM
FIR03-00070 INSP-Final Inspection8/5/20038/6/20038/6/2003 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 8/5/2003 at 9:55:05 AM. Contact: ###-####. this a phased project; phase 1okay; NAC's will be per plans after phase two 8/6/2003 12:33:44 PM
FIR03-00434 INSP-Sprinkler Rough-in8/5/20038/6/20038/6/2003 12:00:00 AMAPART
office underground; Phone #: ###-#### Internet Inspection Request from: Darla Downs stub out okay; thrust block at base of riser okay; need to complete rest of UG to UW tie in 8/6/2003 9:50:58 AM
BLD03-01769 FIRE-Final Inspection8/5/20038/6/20038/6/2003 12:00:00 AMAFAIL
jim; Phone #: ###-#### Internet Inspection Request from: Darla Downs store front door hardware to be openable from the inside without special knowledge; duct detectors are required for HVAC units for unit shutdown; the HVAC units weren't modified for this building permit; the panel is an FCI with what appears to be a free zone for the new detectors; the exsisting FACP will require a map; there is a smoke above the panel and a pull station in the riser/FACP room; horn is in this new permitted space 8/6/2003 10:48:46 AM
FIR03-00336 INSP-Final Inspection8/5/20038/6/20038/6/2003 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 8/5/2003 at 7:05:58 PM. Contact: ###-####.
BLD03-00830 FIRE-Final Inspection8/6/20038/6/20038/6/2003 12:00:00 AMPPART
Phone #: ###-#### Internet Inspection Request from: Rita DeYoungtemp occ approvede per Dave Miller pending resolution of fire sprinklers; need to complete emergency lighting in north hall; complete alarm per latest review 8/7/2003 9:21:19 AM
FIR03-00434 INSP-Sprinkler Rough-in/Hydro8/6/20038/6/20038/6/2003 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 8/6/2003 at 9:27:04 AM. Contact: ###-####. okay to cover the UG; still need hydro and flush 8/6/2003 1:10:02 PM
FIR03-00192 INSP-Sprinkler Rough-in8/6/20038/6/20038/6/2003 12:00:00 AMPPART
test; Phone #: ###-#### Internet Inspection Request from: Linda Hartwell hydro okay; sprinkler system needs annual inspection; needs knox box and signs on door to sprinkler controls 8/7/2003 9:22:24 AM
FIR03-00315 INSP-Final Inspection8/6/20038/6/20038/6/2003 12:00:00 AMPCANC
wrong permit added by inspector 409 8/6/2003 11:06:51 AM
BLD03-00315 FIRE-Final Inspection8/6/20038/6/20038/6/2003 12:00:00 AMPPASS
verfied damper operation - okay; penetrations fire stopped at walls and at new wall for new doors 8/6/2003 12:31:59 PM
FIR03-00259 INSP-Final Inspection8/6/20038/6/20038/6/2003 12:00:00 AMPPASS
FIR03-00225 INSP-Final Inspection8/6/20038/6/20038/6/2003 12:00:00 AMPPASS
BLD02-02815 FIRE-Final Inspection8/6/20038/6/20038/6/2003 12:00:00 AMPPART
data entry and soiled linen area to west aren't completed as part of this phase; alarms and sprinklers are okay for this phase 8/6/2003 12:37:29 PM
FIR03-00039 INSP-Final Inspection8/6/20038/6/20038/6/2003 12:00:00 AMPPASS
this portion of the BLD permit complete; need submittals for the next phase