Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR07-01022 INSP-Final Inspection8/4/20088/6/20088/6/2008 8:20:50 PMPFAIL
Main elevator heat detectors in shaft, test completed.Heat detectors in main elevator control room, test completed. Heat detector in frieght elevator shaft, test complete. Heat detector in frieght elevator control room failed due to short in wiring need to re-test. Panel in trouble. KR
FIR08-00170 INSP-Final Inspection8/5/20088/6/20088/6/2008 8:10:08 PMPPASS
Scope of work per quick permit completed. KR
FIR07-00928 INSP-Sprinkler Rough-in/Hydro8/5/20088/6/20088/6/2008 6:50:20 PMAPART
OH hydrostatic testing for the second, third and fifth floors passed. Noted minor spacing and hanger issues to be repaired on the 6th floor.
FIR08-00255 INSP-Final Inspection8/6/20088/6/20088/6/2008 1:51:00 PMPFAIL
See red line notes on plans for deficiencies and areas tested today per site visit by K. Roule.
FIR08-00350 INSP-Final Inspection8/6/20088/6/20088/6/2008 1:49:37 PMPPASS
Fire sprinkler permit work completed satisfactory, permit finaled.
FIR08-00542 INSP-Sprinkler Rough-in/Hydro8/5/20088/6/20088/6/2008 11:57:06 AMAPART
OH fire sprinkler modifications are acceptable, grid ceiling and pendent heads are not yet installed at the west side, plans do not reflect actual wall layout-however spacing and locations are okay.
FIR07-00606 INSP-Sprinkler Rough-in8/5/20088/6/20088/6/2008 11:06:24 AMAPART
Additional pendent heads at the west side of the auditorium in the angled hard lid soffit are okay for cover pending plans are provided reflecting field installation.
FIR08-00431 INSP-Final Inspection8/6/20088/6/20088/6/2008 11:03:49 AMPCANC
Overbooked
BLD07-01006 FIRE-Alarm Testing8/5/20088/6/20088/6/2008 10:33:28 AMAFAIL
Provide missing EM lights and exit signs at both vestibules on the north side of the auditoriums, also need to post max. occupant load signs per review notes.
BLD05-01094 FIRE-Alarm Testing8/5/20088/6/20088/6/2008 10:30:39 AMAPASS
Fire life safety passed.
BLD06-01081 FIRE-Alarm Testing8/5/20088/6/20088/6/2008 10:30:05 AMAPASS
Fire life safety inspection passed.
BLD08-01553 FIRE-Final Inspection8/5/20088/6/20088/6/2008 9:43:48 AMAPART
Temporary occupancy approval okayed, final pending removal of the remainder of ceiling tiles above the stairs.
FIR08-00452 INSP-Sprinkler Rough-in8/5/20088/6/20088/6/2008 9:13:14 AMANH
This is rough to cover for the 2nd fl. Plans are on site. Brian D is the contact. Thanks Phone #: ###-#### Internet Inspection Request from: Stan Beus ****NOTE: Wrong permit number request, this permit is for basement work in the adjacent building.
FIR08-00270 FIR-Aging Inspection8/6/20088/6/20088/6/2008 9:06:48 AM DEFR
Site construction underway.