BLD07-02160
| FIRE-Final Inspection | 8/5/2009 | 8/6/2009 | 8/6/2009 4:07:26 PM | P | PASS |
|
|
Life safety passed
|
FIR08-00832
| INSP-Final Inspection | 8/6/2009 | 8/6/2009 | 8/6/2009 4:05:33 PM | P | FAIL |
|
|
Todays inspection was for work completed on the first floor residence rooms, which all are. The corridors are not yet complete.
|
FIR08-00830
| INSP-Final Inspection | 8/6/2009 | 8/6/2009 | 8/6/2009 4:02:56 PM | P | FAIL |
|
|
Todays inspection was for work completed on the first floor residence rooms, which all are. The corridors are not yet complete.
|
FIR07-01031
| INSP-Sprinkler Rough-in | 8/5/2009 | 8/6/2009 | 8/6/2009 1:04:02 PM | A | PASS |
|
|
See the city approved plans for locations near the main entrance where the sprinkler piping is ok to cover.
|
FIR09-00460
| INSP-Final Inspection | 8/5/2009 | 8/6/2009 | 8/6/2009 1:02:02 PM | A | FAIL |
|
|
Inspection was actually a conference about electrical shutdown under the hood. I left the IFC code reference at the Simplex office as requested by Dave.
|