Inspections for the day of: Thursday, August 6, 2009.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorClint A Smith
TitleEROSION CONTROL INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC07-00987 BMP Violation8/6/20098/6/20098/6/2009 4:55:53 PMPPASS
All issues from the prior day have been corrected and protected.
ESC08-00491 General Inspection8/6/20098/6/20098/6/2009 4:55:05 PMPPART
Discussed with Epstien over no discharge from turbid water is allowed off site with out special provisions. Was told that they will be installing a head gate at the V cut at the out fall at the basin at the South west end of the project area.
ESC08-00660 General Inspection8/6/20098/6/20098/6/2009 3:55:38 PM PASS
ESC09-00407 BMP Violation8/4/20098/6/20098/6/2009 3:41:08 PMAFAIL
Stop Work Order Posted. See inspection record.
ESC09-00407 INSP - Stop Work Order8/6/20098/6/20098/6/2009 3:39:49 PMPFAIL
Verbal to RP:
STOP WORK ORDER.
1. Protect Storm Drain to the west of lot.
2. Install sediment barriers along the stock piles.
Must call for a re-inspection to have Stop Work Order lifted once all issues are corrected.
ESC09-00067 Site Preparation8/6/20098/6/20098/6/2009 2:47:50 PM NR
ESC09-00457 Site Preparation8/6/20098/6/20098/6/2009 11:50:13 AM PASS
ESC08-00952 Complaint Inspection8/5/20098/6/20098/6/2009 11:37:22 AMAFAIL
Message to RP:
1. Explained to RP that a Construction Exit constructed with crushed basalt rock 4-8 inches depth with a geotextile fabric underneath the rock. This will meet the Erosion Control requirement and also the Fire code requirements. Must occur by the end of the day 8/6/09. Will reinspect on 8/7/09 AM
ESC09-00306 Site Preparation8/6/20098/6/20098/6/2009 10:09:45 AM NR
Will re-inspect in 1 week.
ESC08-00102 BMP Violation8/6/20098/6/20098/6/2009 9:51:08 AMAPART
All issues corrected prior to the inspection being complete.
ESC09-00486 Site Preparation8/6/20098/6/20098/6/2009 9:06:19 AM PART
Need to install a concrete washout prior to pour date of footings.
ESC09-00325 Site Preparation8/6/20098/6/20098/6/2009 9:03:21 AM PASS
Will inspect through out duration of project.
ESC09-00480 Site Preparation8/6/20098/6/20098/6/2009 8:21:50 AM NR