ESC13-00775
| Site Preparation | 8/1/2013 | 8/1/2013 | | P | |
|
|
|
BLD12-01566
| BLD-Final | 8/2/2013 | 8/2/2013 | | P | |
|
|
shane Phone #: ###-####
|
BLD13-00780
| BLD-Conference | 8/6/2013 | 8/6/2013 | 8/7/2013 9:52:10 PM | P | PASS |
|
|
dan Phone #: ###-####,, frame and firewall?s
|
BLD13-02065
| BLD-Framing/Rough-in | 8/5/2013 | 8/6/2013 | 8/7/2013 12:03:33 PM | P | PART |
|
|
jared Phone #: ###-####,, joist connections ok
|
BLD13-01719
| BLD-Conference | 8/6/2013 | 8/6/2013 | 8/7/2013 7:57:03 AM | P | DONE |
|
|
Phone #: ###-#### >> Inspection requested via web by Ira Rutledge
|
BLD10-01236
| BLD-Final | 8/6/2013 | 8/6/2013 | 8/6/2013 3:45:44 PM | P | DONE |
|
|
mike Phone #: ###-####
|
BLD10-01236
| DOC - Permit Finaled | 8/6/2013 | 8/6/2013 | 8/6/2013 3:44:54 PM | P | PASS |
|
|
done
|
BLD13-00801
| BLD-Final | 8/5/2013 | 8/6/2013 | 8/6/2013 2:59:40 PM | A | PEND |
|
|
bob Phone #: ###-####,, pending elec final
|
BLD13-01985
| BLD-Final | 8/5/2013 | 8/6/2013 | 8/6/2013 2:31:52 PM | A | DONE |
|
|
The roof is ready for final inspection. Thank you Phone #: ###-#### >> Inspection requested via web by Michael La Pointe
|
BLD13-02061
| BLD-Final | 8/5/2013 | 8/6/2013 | 8/6/2013 2:15:28 PM | A | DONE |
|
|
The roof is ready for final inspection. Thank you Phone #: ###-#### >> Inspection requested via web by Michael La Pointe
|
BLD13-02061
| DOC - Permit Finaled | 8/6/2013 | 8/6/2013 | 8/6/2013 2:07:07 PM | P | PASS |
|
|
|
BLD13-01962
| BLD-Framing/Rough-in | 8/5/2013 | 8/6/2013 | 8/6/2013 1:38:15 PM | A | PART |
|
|
Scott Phone #: ###-####,, need electrical pass on rough in
|
BLD13-01719
| DOC - Permit Finaled | 8/6/2013 | 8/6/2013 | 8/6/2013 12:34:42 PM | P | PASS |
|
|
|
BLD13-01883
| BLD-Foundation | 8/2/2013 | 8/6/2013 | 8/6/2013 12:22:12 PM | A | PART |
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
ESC13-00427
| General Inspection | 8/6/2013 | 8/6/2013 | | | |
|
|
|