Inspections for the day of: Wednesday, August 6, 2014.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD14-01091 FIRE-Final Inspection8/6/20148/6/20148/7/2014 11:32:01 AMPPASS
Fire life safety inspection passed.
BLD14-00796 FIRE-Conference8/6/20148/6/20148/6/2014 4:48:03 PMPDONE
On site conference with contractor regarding fire life safety conditions and inspection items necessary for final. Noted door hardware issues, one exit sign to be repaired, noted curtain partitions are not yet installed and may create obstructions to fire alarm and sprinkler coverage.
FIR14-00438 INSP-Final Inspection8/5/20148/6/20148/6/2014 4:41:34 PMAPASS
Verified previous correction items. Functional testing passed. Fire alarm permit finaled.
BLD14-00512 FIRE-Final Inspection8/4/20148/6/20148/6/2014 4:39:54 PMPPASS
Fire life safety inspection passed.
FIR13-00723 INSP-Sprinkler Rough-in8/6/20148/6/20148/6/2014 4:39:26 PMPPART
Okay to cover fire sprinkler work at the 1st floor lobby ceiling and aeronautics office as marked and dated on plans. Noted one head to be relocated at the west open office area.
FIR14-00103 INSP-Supply line flush8/6/20148/6/20148/6/2014 1:38:32 PMPCANC
Jeremiah is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
FIR14-00103 INSP-Sprinkler Rough-in/Hydro8/6/20148/6/20148/6/2014 1:38:30 PMPCANC
This is an ug hydro. Jeremiah is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
FIR13-00460 INSP-Final Inspection8/6/20148/6/20148/6/2014 11:47:52 AMAPASS
UG fire supply line flush completed satisfactory. Scope of permit work finished. Permit finaled.
FIR14-00308 INSP-Final Inspection8/4/20148/6/20148/6/2014 10:59:55 AMAPASS
Fire alarm work passed inspection and testing. Permit finaled.
FIR14-00285 INSP-Final Inspection8/5/20148/6/20148/6/2014 10:59:10 AMAPASS
Fire sprinkler permit work passed final walkthrough.
BLD14-00119 FIRE-Final Inspection8/5/20148/6/20148/6/2014 10:58:25 AMAPASS
Fire life safety inspection completed satisfactory.
FIR14-00497 INSP-Alarm Testing8/5/20148/6/20148/6/2014 10:57:32 AMAPART
Functional testing completed acceptable. Final pending location of smoke detectors at the north and south corridors 154 and 162 east side of the new fire doors. Relocate away from HVAC diffusers or delete and meet NFPA 72 17.7.5.6.1.
FIR14-00270 INSP-Sprinkler Rough-in8/5/20148/6/20148/6/2014 10:51:20 AMAPART
Overhead work at the front office area grid ceilings approved for cover. Need to adjust spacing at three locations in warehouse 117 per plan annotations- four heads exceed min. spacing, one head overspaced off new demising wall.
FIR14-00327 INSP-Final Inspection8/5/20148/6/20148/6/2014 9:18:46 AMAPASS
Scope of work completed. Fire sprinkler permit finaled.