Inspections for the day of: Wednesday, August 6, 2014.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorChad Schwendiman
TitleMEC-INSPECTOR
Phone #780-9549
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC14-03189 Pressure Test7/31/20148/6/20148/6/2014 4:41:10 PMPPASS
gaspiper Miguel ###-#### Phone #: ###-#### >> Inspection requested via web by Dustin Rich - 20LB GAS PRESSURE PASS
MEC14-02894 Final8/5/20148/6/20148/6/2014 4:19:48 PMPNR
As late as possible in the afternoon with call Tyrel ###-####. Thanks Phone #: ###-#### >> Inspection requested via web by Allie Courter
MEC14-02894 Pressure Test8/5/20148/6/20148/6/2014 4:04:46 PMPPASS
As late as possible in the afternoon with call Tyrel ###-####. Thanks Phone #: ###-#### >> Inspection requested via web by Allie Courter - 20LB GAS PRESSURE PASS
MEC14-03335 Final8/6/20148/6/20148/6/2014 3:44:38 PMPPASS
Call Eric @ ###-#### to coordinate inspection time. Phone #: ###-#### >> Inspection requested via web by Angie Maguire
MEC14-03335 Pressure Test8/6/20148/6/20148/6/2014 3:43:57 PMPPASS
need flue pressure test inspection for high eff furnace installation. Call Eric @ ###-#### to coordinate inspection time. Phone #: ###-#### >> Inspection requested via web by Angie Maguire - 5LB FLUE PRESSURE PASS
MEC14-03339 Final8/6/20148/6/20148/6/2014 2:55:35 PMPPASS
Phone #: ###-#### >> Inspection requested via web by April Thomas
MEC14-03155 Final8/6/20148/6/20148/6/2014 2:25:50 PMPPASS
>> Inspection requested via web by Joe Bertwell
MEC14-03155 Pressure Test8/6/20148/6/20148/6/2014 2:25:23 PMPPASS
>> Inspection requested via web by Joe Bertwell - 20LB GAS PRESSURE PASS
MEC14-00698 Rough-in8/6/20148/6/20148/6/2014 1:58:59 PMPPASS
Pressure test for tubing. 2pm please. Phone #: ###-#### >> Inspection requested via web by April Thomas - 100LB HYDRONIC TUBE PRESSURE TEST PASS FOR FLOOR HEAT IN THE HOUSE.
MEC14-03292 Final8/6/20148/6/20148/6/2014 1:28:10 PMPPASS
Jeff Phone #: ###-####
MEC14-00318 Final8/6/20148/6/20148/6/2014 12:45:39 PMAPASS
The gas test is done, this should have been finaled out.
MEC14-02996 Pressure Test8/6/20148/6/20148/6/2014 11:17:39 AMAPASS
Can you make it a pm inspection Phone #: ###-#### >> Inspection requested via web by anthony allen - 60LB GAS PRESSURE PASS
MEC14-03296 Final8/5/20148/6/20148/6/2014 10:53:48 AMAPASS
This is a Flue Pressure and Final Inspect. Pls meet our installer
at home at 10 AM . Install Mgr, Allen, Ph is ###-####.
Phone #: ###-#### >> Inspection requested via web by Mary LaFayette
MEC14-03328 Final8/5/20148/6/20148/6/2014 10:20:44 AMAPASS
Mechanic Final on HVAC installation of A/C - Please contact Angie with any further questions ###-#### Phone #: ###-#### >> Inspection requested via web by Bailey Esposito
MEC14-03204 Final8/6/20148/6/20148/6/2014 9:42:27 AMPPASS
joe cusik Phone #: ###-####
MEC14-01843 Rough-in8/5/20148/6/20148/6/2014 9:24:42 AMAPART
lineset inspection Phone #: ###-#### >> Inspection requested via web by Brandon Sorensen - Shaft okay to cover 1st. 3rd. & 4th. floors, 1st. floor units okay to cover, 2nd. 3rd. & 4th. floors okay to cover on the south wing.