ELE14-02121
| Electrical Rough-In | 8/6/2014 | 8/6/2014 | 8/6/2014 3:12:14 PM | P | PASS |
|
|
wall cover is needed call steve with any questions ###-#### Phone #: ###-#### Inspection requested via web by Don Lustig rough-in ok cover walls
|
ELE14-02141
| Electrical Rough-In | 8/5/2014 | 8/6/2014 | 8/6/2014 2:34:25 PM | P | PASS |
|
|
bonding ; underground Phone #: ###-#### Inspection requested via web by Louis Keller rough-in ok cover bonding and underground conduits from pool shell to equipment location
|
ELE14-02150
| Temporary Service | 8/6/2014 | 8/6/2014 | 8/6/2014 2:02:33 PM | P | FAIL |
|
|
Temp pole Phone #: ###-#### Inspection requested via web by Lars Johnson Overhead temporary requires 6X6 presure treaded timber
|
ELE13-02849
| Final | 8/5/2014 | 8/6/2014 | 8/6/2014 1:41:18 PM | P | PART |
|
|
Contact is Alan Krishnek. This is a partial final in the PACU unit. Phone #: ###-#### Inspection requested via web by Scott Campbell Partial final ok PACU
|
ELE13-02849
| Electrical Rough-In | 8/6/2014 | 8/6/2014 | 8/6/2014 1:40:04 PM | P | PASS |
|
|
Contact is Alan Krishnek. This is a partial final in the PACU unit. Phone #: ###-#### Inspection requested via web by Scott Campbell Rough-in ok cover lobby walls
|
ELE14-02118
| Rough-In Permanent Service | 8/6/2014 | 8/6/2014 | 8/6/2014 1:18:31 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Heath Thomas rough-in p/s u/g n ok
|
ELE14-01295
| Rough-In Permanent Service | 8/5/2014 | 8/6/2014 | 8/6/2014 1:07:45 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Jerry Moore p/s u/g n ok
|
ELE12-00179
| ELE-Aging Inspection | 8/6/2014 | 8/6/2014 | 8/6/2014 11:10:55 AM | | DONE |
|
|
still under construction
|
ELE14-01355
| Final | 8/5/2014 | 8/6/2014 | 8/6/2014 11:09:05 AM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by ERIC CENTERS Kitchen small applance GFCI won't reset, (southside)
|
ELE14-01849
| Electrical Rough-In | 8/5/2014 | 8/6/2014 | 8/6/2014 10:31:37 AM | A | PART |
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Partial rough-in ok cover outside perimeter walls as per highlighted in pink and dated on job site plans
|
ELE14-01595
| Electrical Rough-In | 8/6/2014 | 8/6/2014 | 8/6/2014 9:35:51 AM | A | PART |
|
|
underground rough-in partial underground cover center section first layer
|
ELE14-01722
| Final | 8/6/2014 | 8/6/2014 | 8/6/2014 9:00:07 AM | A | PASS |
|
|
Contact: Mike Ennis Phone #: ###-#### Inspection requested via web by Deb Gooden final ok for bld14-0168 also
|
ELE14-01544
| Final | 8/5/2014 | 8/6/2014 | 8/6/2014 8:46:05 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by daniel bibikov correction done, final ok duplex
|
ELE14-01359
| Final | 8/5/2014 | 8/6/2014 | 8/6/2014 8:23:07 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Lee VanSchoiack No card on site final ok
|
ELE14-01358
| Final | 8/5/2014 | 8/6/2014 | 8/6/2014 8:19:10 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Lee VanSchoiack No card on site final ok
|
ELE14-02086
| Electrical Rough-In | 8/5/2014 | 8/6/2014 | 8/5/2014 2:22:55 PM | A | FAIL |
|
|
Jordan Phone #: ###-#### BCC and Idaho Power requirement Overhead service raiser, shall be 2 in.IMC if point of attachement NEC 250.96 Bonding of enclosures NEC 312.5(c) Cables shall be secured to cabnets, cutout boxes at entry NEC 200.6 Means of identifying grounded conductors
|