BLD01-00940
| BLD-Final | 8/3/2001 | 8/7/2001 | 8/7/2001 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 08/03/2001 at 11:09:23. Contact: ###-####.c/n posted. 8/7/2001 10:26:21 AM
|
BLD01-00650
| BLD-Concrete | 8/6/2001 | 8/7/2001 | 8/7/2001 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 08/06/2001 at 08:43:27. Contact: ###-####.s-i on site. 8/7/2001 12:07:03 PM
|
BLD01-00644
| BLD-Concrete | 8/6/2001 | 8/7/2001 | 8/7/2001 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 08/06/2001 at 08:44:32. Contact: ###-####.s-i on site. 8/7/2001 12:07:19 PM
|
BLD01-01340
| BLD-Framing/Rough-in | 8/6/2001 | 8/7/2001 | 8/7/2001 12:00:00 AM | A | FAIL |
|
|
###-####. need to address prior c/n for micro lams reqd,bed 2 and garage. 8/7/2001 9:49:59 AM
|
BLD01-01340
| BLD-Energy code compliance | 8/6/2001 | 8/7/2001 | 8/7/2001 12:00:00 AM | A | PART |
|
|
|
BLD00-02811
| BLD-Final | 8/7/2001 | 8/7/2001 | 8/7/2001 12:00:00 AM | P | NR |
|
|
###-####
|
BLD01-01601
| BLD-Conference | 8/7/2001 | 8/7/2001 | 8/7/2001 12:00:00 AM | P | PART |
|
|
for conference- brandon ###-#### . sujecsted they talk with engineer about entry modifications and int wall header etc not per plan. 8/7/2001 4:46:20 PM
|
BLD01-00588
| BLD-Conference | 8/7/2001 | 8/7/2001 | 8/7/2001 12:00:00 AM | P | PART |
|
|
###-#### MATT
. working on shafts for grease hoods, 8/7/2001 3:46:32 PM
|
MIS01-00152
| BLD-Conference | 8/7/2001 | 8/7/2001 | 8/7/2001 12:00:00 AM | P | PART |
|
|
Scheduled by Inspector: 415 On 8/7/2001 12:30:23 PM . no structural work, moved existing counter forward, changed out a 3 compartment sink,added a type 2 hood over an oven, talked with tennant and told him to go into the office and seek info for obtaining any neccessary permits. 8/7/2001 3:45:57 PM
|