Inspections for the day of: Monday, August 7, 2017.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR17-00305 INSP-Sprinkler Rough-in8/4/20178/7/20178/7/2017 3:24:31 PMAPART
Rough to cover for 7'-0" from the building only. The remaining piping was not installed by Shilo. A separate permit will be required for this work from a licensed sprinkler contractor or Shilo will need to accept responcibility for this work. Shilo will need to resubmit plans for a change of scope. Plans need to be submitted showing the additional fittings in the underground supply line. Per Brian, the installer, the top of pipe is 5'-1" at the doorway/floor and is at 4'-9" at the connection. There is no sidewalk or land scaping just smooth travel from the door to the low point in the parking lot. If changes are made in the parking lot piping will need to be dug up and modified to the correct depth.
FIR17-00198 INSP-Sprinkler Rough-in/Hydro8/7/20178/7/20178/7/2017 1:51:25 PMPPASS
Underground hydro test passed
FIR17-00405 INSP-Sprinkler Rough-in8/4/20178/7/20178/7/2017 11:49:37 AMAPASS
Rough-in passed. Piping can be covered.
FIR17-00278 INSP-Sprinkler Rough-in8/4/20178/7/20178/7/2017 11:47:15 AMAPASS
Rough-in passed. Piping can be covered.
FIR17-00359 INSP-Final Inspection8/4/20178/7/20178/7/2017 10:33:40 AMAPASS
Permit finaled
NAF17-00053 INSP-Final8/4/20178/7/20178/7/2017 12:00:00 AMAPASS
Phone #: 2088698456 >> Inspection requested via mobile web by Wes Flacker-