PLM19-03218
| Other | 8/6/2019 | 8/7/2019 | 8/7/2019 3:56:48 PM | P | FAIL |
|
|
1:30 conferance 1. Relocate solar storage tank off the platform. The water heater must be readily accessible. 2. Insulate the solar water lines the entire distance. 3. Install a bleeder valve on the solar panals at the high point. 4. provide written instructions for winterization of the thermal system. 5. Tag all valves with their functions. 6. All work must be done by the permit holder or a licensed Journeyman.
|
PLM19-03275
| Plumbing Rough-in | 8/7/2019 | 8/7/2019 | 8/7/2019 2:55:59 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Kristy Watson
|