ELE00-01269
| Electrical Rough-In | 8/4/2000 | 8/8/2000 | 8/8/2000 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 08/04/2000 at 09:16:59. Contact: . 2 bathrooms & mech. rm. ceiling ele. R/I 8/8/00 3:35:10 PM
|
ELE00-00836
| Final | 8/7/2000 | 8/8/2000 | 8/8/2000 12:00:00 AM | A | PASS |
|
|
John ###-#### Project completed 8/8/00 3:34:16 PM
|
ELE00-03004
| Electrical Rough-In | 8/7/2000 | 8/8/2000 | 8/8/2000 12:00:00 AM | A | PART |
|
|
tom ###-#### Conference; grounding/patient facility. Service. 8/8/00 3:34:53 PM
|
ELE00-02767
| Electrical Rough-In | 8/7/2000 | 8/8/2000 | 8/8/2000 12:00:00 AM | P | PART |
|
|
ufer ground Jess ###-#### Groundwork; PVC in trench ok; concrete ok. 8/8/00 3:35:41 PM
|
ELE00-00983
| Final | 8/8/2000 | 8/8/2000 | 8/8/2000 12:00:00 AM | P | PART |
|
|
###-#### Temp. occ. in garage area only 8/8/00 3:36:11 PM
|
ELE00-03050
| Electrical Rough-In | 8/8/2000 | 8/8/2000 | 8/8/2000 12:00:00 AM | P | FAIL |
|
|
SKIP ###-#### R/I No access; called contractor, left card. Will reschedule 8/8/00 3:35:59 PM
|
ELE00-02039
| Final | 8/8/2000 | 8/8/2000 | 8/8/2000 12:00:00 AM | P | PASS |
|
|
mark ###-#### Project completed ok 8/8/00 3:34:05 PM
|
ELE00-03054
| Electrical Rough-In | 8/8/2000 | 8/8/2000 | 8/8/2000 12:00:00 AM | P | PART |
|
|
###-#### West wall, ele. R/I 8/10/00 11:25:08 AM
|