ESC09-00352
| General Inspection | 8/8/2011 | 8/8/2011 | 8/8/2011 3:33:15 PM | | PART |
|
|
Areas not being worked that needs stabilization. All wood debris has been chipped and removed from site. Green up inside the park area continues.
|
ESC10-00918
| General Inspection | 8/8/2011 | 8/8/2011 | 8/8/2011 3:25:18 PM | | PART |
|
|
Structures completed, working on site stabilization. Bare ground has been installed with many l. feet of sediment barriers, (straw wattles). Some straw blankets installed, rp could not tell me if seeding had taken place prior to seeding or not. Options discussed and basic information regarding proper re-stabilization took place. I informed RP that Boise City needs re-vegetation (at least 70%) to completed the terms of the ESC permit.
|
ESC10-00750
| Site Preparation | 8/8/2011 | 8/8/2011 | 8/8/2011 2:41:30 PM | P | PART |
|
|
Verbal to RP, replace drop inlet protection from filter fabric to appr. products, e.x.Brooksome, Ultra Drain, (witched hats). As well, post sign where visuable to the general public. Completd by end of the week.
|
ESC11-00550
| Site Preparation | 8/8/2011 | 8/8/2011 | 8/8/2011 2:02:18 PM | | NR |
|
|
|