Inspections for the day of: Friday, August 8, 2014.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
NAF14-00005 INSP-Sprinkler Rough-in/Hydro8/8/20148/8/20148/8/2014 3:31:03 PMPPART
Upper level/second floor piping is ok to cover. Can not cover the lower level piping untill a re-inspection verifies that seismic bracing on the branchlines has been completed.
FIR14-00518 INSP-Final Inspection8/8/20148/8/20148/8/2014 2:59:42 PMPFAIL
Provide city approved data sheets and as-builts/submittals as discussed. Functional testing of system passed.
FIR14-00517 INSP-Final Inspection8/8/20148/8/20148/8/2014 2:56:08 PMPFAIL
Provide city approved data sheets and as-built drawings/complete submittals as dsicussed. Functional testing of system passed.
FIR14-00177 INSP-Sprinkler Rough-in8/7/20148/8/20148/8/2014 12:57:57 PMAPASS
Remaining underground supply piping is ok to cover.
BLD14-01771 FIRE-Final Inspection8/8/20148/8/20148/8/2014 11:05:28 AMPPASS
Life safety passed
BLD14-01781 FIRE-Final Inspection8/8/20148/8/20148/8/2014 11:05:10 AMPPASS
Life safety passed
FIR14-00115 INSP-Sprinkler Rough-in/Hydro8/7/20148/8/20148/8/2014 11:04:25 AMAPASS
Overhead hydro test of the existing hanger passed
BLD14-01771 FIRE-Final Inspection8/7/20148/8/20148/8/2014 9:23:11 AMAFAIL
Hang fire extinguishers and repair exit signs
BLD14-01781 FIRE-Final Inspection8/7/20148/8/20148/8/2014 9:22:43 AMAFAIL
Hang fire extinguishers and repair exit signs
FIR14-00497 INSP-Final Inspection8/8/20148/8/20148/8/2014 7:54:51 AMAPASS
Permit finaled
FIR14-00280 INSP-Final Inspection8/7/20148/8/20148/7/2014 2:17:14 PMAPASS
Permit finaled