Inspections for the day of: Thursday, August 9, 2001.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRuss Owen
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD01-01233 BLD-Aging Inspection8/9/20018/9/20018/9/2001 12:00:00 AM PART
wip. 8/13/2001 12:50:13 PM
BLD01-00900 BLD-Final8/2/20018/9/20018/9/2001 12:00:00 AMAFAIL
late pm please gary ###-####. needs mec and ele finaled and safety glass at rear patio ,also note ,zoning department approval for existing garage and house,see note from Dave Abo do not final. 8/9/2001 9:36:07 AM
BLD01-01659 BLD-Framing/Rough-in8/8/20018/9/20018/9/2001 12:00:00 AMAPART
R/I - ROBERT -UMENTUM -- ###-#### -CALL 1ST BEFORE INSP. New door frame ok, need to have the new exterior elevated concrete landing approved by office. do not pour. 8/9/2001 10:42:18 AM
BLD01-00658 BLD-Framing/Rough-in8/8/20018/9/20018/9/2001 12:00:00 AMAPASS
###-####. ok to sheetrock 8/9/2001 9:54:49 AM
BLD00-03498 BLD-Conference8/8/20018/9/20018/9/2001 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 08/08/2001 at 17:13:31. Contact: ###-####. 8/9/2001 12:12:32 PM
BLD00-02769 BLD-Framing/Rough-in8/9/20018/9/20018/9/2001 12:00:00 AMPFAIL
###-#### john fr insp
BLD01-00588 BLD-Conference8/9/20018/9/20018/9/2001 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 08/09/2001 at 07:35:05. Contact: ###-####.. need to sheetrock above shafts, built as per detail, NOTE: detail porly drawn at roof penetration of shafts now constructed But constructed as per plans. 8/9/2001 4:25:04 PM
BLD00-02811 BLD-Final8/9/20018/9/20018/9/2001 12:00:00 AMPNR
tim ###-#### fn occ
BLD01-01618 BLD-Framing/Rough-in8/9/20018/9/20018/9/2001 12:00:00 AMPNR
r/i ben - ###-#### fr . needs electrical inspection ,I talked with contracor told him insulation inspection is required on this it is heated space. see plan note. 8/9/2001 3:28:59 PM