BLD05-01403
| FIRE-Final Inspection | 8/9/2005 | 8/9/2005 | 8/9/2005 3:28:13 PM | P | PASS |
|
|
Fire life safety finaled.
|
FIR05-00372
| INSP-Sprinkler Rough-in | 8/8/2005 | 8/9/2005 | 8/9/2005 1:58:56 PM | A | FAIL |
|
|
Missing 4-way EQ brace on atrium main, heads in east soffit are overspaced, one line is installed as 1" pipe--the plan shows 11/4 pipe, missing head in lower west soffit hard lid, need to verify there are no obstructions to coverage caused at the juncture of soffits and grid ceiling when the grid is installed.
|
MIS05-00118
| FIR-Final | 8/8/2005 | 8/9/2005 | 8/9/2005 12:52:40 PM | A | FAIL |
|
|
thomas ###-#### --Need to provide suite address numbers as discussed, provide fire extinguisher mounted on the wall with a current annual inspection tag.
|
BLD04-02044
| FIRE-Final Inspection | 8/8/2005 | 8/9/2005 | 8/9/2005 12:06:43 PM | A | PASS |
|
|
Life safety passed inspection.
|
FIR05-00385
| INSP-Sprinkler Rough-in/Hydro | 8/8/2005 | 8/9/2005 | 8/9/2005 11:26:09 AM | A | PART |
|
|
UG fire supply line hydrostatic test for phase one and two of underground work passed inspection.
|
FIR05-00385
| INSP-Supply line flush | 8/8/2005 | 8/9/2005 | 8/9/2005 11:23:34 AM | A | PART |
|
|
Phase two UG fire supply line flush is satisfactory.
|
BLD04-02481
| FIRE-Final Inspection | 8/8/2005 | 8/9/2005 | 8/9/2005 9:55:41 AM | A | PASS |
|
|
Life safety finaled.
|
FIR04-00812
| INSP-Supply line flush | 8/9/2005 | 8/9/2005 | 8/9/2005 12:00:00 AM | A | PART |
|
|
Two hour hydrostatic test and supply line flush both passed inspection.
|
FIR05-00351
| INSP-Final Inspection | 8/9/2005 | 8/9/2005 | 8/9/2005 12:00:00 AM | P | PASS |
|
|
Overhead fire sprinkler permit finaled.
|