Inspections for the day of: Tuesday, August 9, 2005.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR05-00448 INSP-Sprinkler Rough-in8/9/20058/9/20058/10/2005 9:07:53 AMPPART
Please call prior to inspection jeff; Phone #: ###-####
Rough-in is passed. Items that need corrected are uprights located along a north/south draft stop are spaced at 156 sq. ft. Contractor needs to provide verification that this spacing is approved. Also one upright head needs to be re-installed to correct an overspacing issue. See plans for location. The existing insulation that is installed on the underside of the roof deck is falling on the sprinkler piping and creating obstructions and needs repaired prior to installation of the ceiling tile. Annual inspection is needed and spare heads need to be placed in head box. Final spacing of pendants will be verified when t-bar and ceiling tile is installed. New hvac unit may create obstruction to uprights when installed and will need to be verified. Fire alarm panel is in trouble condition.
FIR05-00170 INSP-Final Inspection8/9/20058/9/20058/9/2005 4:02:35 PMPPASS
(dry system trip test)call Jonathan for details. Thanks; Phone #: ###-####
Dry system tripped in 34.9 seconds. Monitoring agency received signals. Permit finaled.
FIR04-00664 INSP-Sprinkler Rough-in/Hydro8/8/20058/9/20058/9/2005 4:01:41 PMPFAIL
Contact: Chris Lamb - Hydro Test Wet And Anti Freeze system; Phone #: ###-####
Hydro test of the anti-freeze loop failed and the overhead wet system would have passed if the piping from the check valve to the FDC had been included. Need to retest system
BLD05-01202 FIRE-Final Inspection8/9/20058/9/20058/9/2005 3:19:51 PMPFAIL
shawn--fire life safely; Phone #: ###-####
Provide fire extinguishers per review comment #4. Provide approved door hardware per review comments #6 & #7
FIR05-00416 INSP-Final Inspection8/8/20058/9/20058/9/2005 3:16:36 PMPPASS
Fire alarm finaled
BLD05-00755 FIRE-Final Inspection8/9/20058/9/20058/9/2005 3:14:02 PMPPASS
Fire life safety finaled
FIR05-00170 INSP-Alarm Testing8/9/20058/9/20058/9/2005 3:00:04 PMPPASS
(dry system trip test)call Jonathan for details. Thanks; Phone #: ###-####
Dry system tripped in 34.9 seconds. Monitoring agency received signals. Permit finaled.
FIR05-00478 INSP-Supply line flush8/9/20058/9/20058/9/2005 12:28:13 PMPPART
Inspection was for cover of the supply piping located under the walkway. See approved drawings for exact location. No thrust blocking has been done yet.
FIR05-00333 INSP-Final Inspection8/8/20058/9/20058/9/2005 12:26:51 PMAPASS
Permit finaled
FIR05-00197 INSP-Final Inspection8/9/20058/9/20058/9/2005 12:17:55 PMPPASS
Fire sprinkler permit finaled
FIR05-00129 INSP-Final Inspection8/9/20058/9/20058/9/2005 11:52:52 AMPPASS
fire sprinkler permit finaled
BLD04-02272 FIRE-Final Inspection8/8/20058/9/20058/9/2005 11:38:37 AMAFAIL
ben ; Phone #: ###-#### The hvac units still will not go into heat mode for testing. Sample tubes have been fixed.
BLD05-01421 FIRE-Final Inspection8/9/20058/9/20058/9/2005 10:49:28 AMPPASS
Life safety finaled
MIS05-00100 FIR-Final8/8/20058/9/20058/9/2005 10:42:21 AMAPASS
jeff; Phone #: ###-#### Life safety finaled
FIR05-00324 INSP-Final Inspection8/8/20058/9/20058/9/2005 10:27:02 AMAPASS
fire alarm permit finaled
FIR05-00124 INSP-Sprinkler Rough-in/Hydro8/8/20058/9/20058/9/2005 9:10:57 AMAPASS
Eq bracing on the cpvc main is done and the pendant heads are now correct. Need to inspect the dry system and hydro test the wet system and all other final items.