FIR06-00328
| INSP-Sprinkler Rough-in | 8/8/2006 | 8/9/2006 | 8/9/2006 4:05:09 PM | P | PASS |
|
|
Riser room and the electrical room piping rough-ins are passed and the piping can be covered.
|
BLD04-02856
| FIRE-Final Inspection | 8/8/2006 | 8/9/2006 | 8/9/2006 4:03:52 PM | P | FAIL |
|
|
Need fire alarm permit finaled then life safety can be finaled.
|
FIR06-00554
| INSP-Final Inspection | 8/8/2006 | 8/9/2006 | 8/9/2006 3:27:19 PM | A | FAIL |
|
|
Inspection was for rough-in only. Sprinkler piping is ok to cover.
|
FIR05-00536
| INSP-Sprinkler Rough-in | 8/8/2006 | 8/9/2006 | 8/9/2006 1:52:03 PM | A | PASS |
|
|
Breakdown room is ok to cover
|
FIR06-00506
| INSP-Final Inspection | 8/8/2006 | 8/9/2006 | 8/9/2006 1:23:10 PM | A | FAIL |
|
|
No testing performed since the pulls stations had been mounted too high. Candella's for the strobes was incorrect but Tony corrected it as I waited.
|
BLD06-00008
| FIRE-Conference | 8/8/2006 | 8/9/2006 | 8/9/2006 1:22:03 PM | A | DONE |
|
|
Went over fire extinguisher placement with contractor
|