ELE10-02651
| ELE-Aging Inspection | 8/9/2012 | 8/9/2012 | 8/16/2012 10:15:02 AM | | DONE |
|
|
still under construction
|
ELE12-01995
| Final | 8/9/2012 | 8/9/2012 | 8/9/2012 5:09:12 PM | P | PASS |
|
|
final ok
|
ELE12-01746
| Final | 8/9/2012 | 8/9/2012 | 8/9/2012 5:08:54 PM | P | PASS |
|
|
final ok
|
ELE12-01411
| Final | 8/8/2012 | 8/9/2012 | 8/9/2012 5:03:43 PM | P | PART |
|
|
BUSTER. FINAL NORTH SIDE. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy Partial final North half ok to temporary occupancy
|
ELE12-01976
| Rough-In Permanent Service | 8/9/2012 | 8/9/2012 | 8/9/2012 3:14:57 PM | P | PASS |
|
|
>> Inspection requested via web by mike brown rough-in p/s u/g n ok
|
GCE12-00123
| GCE-Permanent Service | 8/8/2012 | 8/9/2012 | 8/9/2012 2:39:42 PM | P | PASS |
|
|
Mike @ ###-#### PM Inspection p/s o/h rec ok
|
ELE12-01489
| Rough-In Permanent Service | 8/9/2012 | 8/9/2012 | 8/9/2012 2:21:53 PM | P | PASS |
|
|
Eric Phone #: ###-#### rough-in p/s u/g n ok
|
ELE12-01489
| Rough-In Permanent Service | 8/9/2012 | 8/9/2012 | 8/9/2012 2:19:08 PM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Eric Brown rough-in p/s u/g n ok
|
ELE12-01956
| Rough-In Permanent Service | 8/9/2012 | 8/9/2012 | 8/9/2012 1:53:12 PM | P | PASS |
|
|
please call 30min prior - mitch Phone #: ###-#### p/s o/h rec ok (single meter only) p/s o/h rec ok
|
ELE12-01503
| Final | 8/9/2012 | 8/9/2012 | 8/9/2012 12:48:18 PM | A | PASS |
|
|
lock box is on left post at the front porch, combo is 2343 Phone #: ###-#### >> Inspection requested via web by Brad Girard final ok
|
ELE12-01981
| Permanent Service | 8/8/2012 | 8/9/2012 | 8/9/2012 12:37:24 PM | P | PASS |
|
|
Please inspect as close to noon as you are able to, as Idaho Power is scheduled for 1:00 PM to replace the high-line from their pole to our new mast. Thank You !!!!! Dan. Phone #: ###-#### >> Inspection requested via web by Dan Mitchell p/s o/h rec ok
|
ELE12-01947
| Rough-In Permanent Service | 8/8/2012 | 8/9/2012 | 8/9/2012 10:21:38 AM | A | PASS |
|
|
Lockbox code 0717, any questions, please call Clay. Thank You. Phone #: ###-#### >> Inspection requested via web by Clay Morgan rough-in p/s o/h rec ok
|
ELE12-01581
| Final | 8/8/2012 | 8/9/2012 | 8/9/2012 9:40:37 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Mark M final ok
|
ELE12-01760
| Electrical Rough-In | 8/9/2012 | 8/9/2012 | 8/9/2012 9:40:09 AM | A | PASS |
|
|
desk phone ###-#### Phone #: ###-#### >> Inspection requested via web by Mark M rough-in ok cover ceiling grid
|
ELE11-00528
| ELE-Aging Inspection | 8/9/2012 | 8/9/2012 | 8/9/2012 9:24:26 AM | | DONE |
|
|
electrical contractor will call for final when he gets back from Hot August Nights
|
GCE11-00151
| GCE-Final | 8/8/2012 | 8/9/2012 | 8/9/2012 9:14:15 AM | A | PASS |
|
|
(Mandatory Inspection) ###-#### PM inspection requested for today please. final ok
|
ELE12-01989
| Electrical Rough-In | 8/8/2012 | 8/9/2012 | 8/9/2012 8:36:35 AM | A | PASS |
|
|
underground inspection for two floor boxes side by side, call for access instructions Phone #: ###-#### >> Inspection requested via web by steve sellers rough-in ok cover underground, 2 floor boxes
|
ELE12-01990
| Rough-In Permanent Service | 8/8/2012 | 8/9/2012 | 8/9/2012 8:21:51 AM | A | PASS |
|
|
early a.m. please Phone #: ###-#### >> Inspection requested via web by daniel bibikov rough-in p/s u/g n ok
|
ELE12-01949
| Rough-In Permanent Service | 8/8/2012 | 8/9/2012 | 8/8/2012 3:41:44 PM | A | PASS |
|
|
READY NOW Phone #: ###-#### >> Inspection requested via web by Bob Glenn rough-in p/s u/g n ok
|
GCE12-00114
| GCE-Rough-In | 8/8/2012 | 8/9/2012 | 8/8/2012 1:41:04 PM | A | PASS |
|
|
Shane @ ###-#### Requested underground inspection rough-in ok cover underground conduits
|