Inspections for the day of: Thursday, August 9, 2012.
Number of inspections: 12
Percentage of inspections complete: 92 %
Percentage of inspections not complete: 8 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC12-00018 Site Preparation8/3/20128/3/2012   
ESC12-00692 Random Inspection8/9/20128/9/20128/9/2012 4:27:07 PMPPART
Noted excavation work in progress for water and sewer lines. Contractor will sweep all silts from hard surfaces at end of work day.
ESC12-00695 Random Inspection8/9/20128/9/20128/9/2012 4:26:52 PMPPART
Noted excavation work in progress for water and sewer lines. Contractor will sweep all silts from hard surfaces at end of work day.
BLD12-01767 BLD-Energy code compliance8/9/20128/9/20128/9/2012 4:25:13 PMPPASS
rick Phone #: ###-####. Rigid foam insulation at interior side of stemwall.
BLD12-01764 BLD-Energy code compliance8/9/20128/9/20128/9/2012 4:24:40 PMPPASS
rick Phone #: ###-####. Rigid foam insulation at interior side of stemwall.
ESC12-00163 Random Inspection8/9/20128/9/20128/9/2012 2:38:35 PMPPASS
All issues have been resolved.
BLD12-00382 BLD-Foundation8/9/20128/9/20128/9/2012 2:36:30 PMPPART
Pouring at 1 footing/foundation - -Mike Phone #: ###-####. Special inspector on site. Also reviewed special inspection contract and verified the special inspection agency is working for the owner.
ESC12-00597 Random Inspection8/9/20128/9/20128/9/2012 9:50:43 AMAPASS
BLD12-01556 BLD-Wall Bracing8/8/20128/9/20128/9/2012 9:50:32 AMAFAIL
zach Phone #: ###-####. No approved plans on site.
BLD08-00986 BLD-Final8/8/20128/9/20128/9/2012 9:15:21 AMAPASS
morgan please call 30 min before going out he would like to be there Phone #: ###-####. Ok for perm occ.
ESC08-00407 Site Final8/9/20128/9/20128/9/2012 9:14:54 AMADONE
ESC08-00407 DOC - Permit Finaled8/9/20128/9/20128/9/2012 9:14:47 AMPPASS