Inspections for the day of: Wednesday, August 9, 2017.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00763 INSP-Sprinkler Rough-in8/8/20178/9/20178/10/2017 4:16:45 PMACANC
Inspection request was for FIR16-00698, this inspection request is cancelled.
NAF17-00049 INSP-Final8/9/20178/9/20178/9/2017 3:01:08 PMPDONE
No fire sprinklers, fire alarm inspection is complete, fire extinguishers are in place with current inspection tags, knox box is mounted on the northeast side of building. Final life fire safety inspection for area of work passed/complete.
FIR16-00586 INSP-Sprinkler Rough-in8/9/20178/9/20178/9/2017 2:25:40 PMPPART
Rough to cover inspection for south side of elevator lobby, level 4 overhead fire sprinkler piping/pendant heads complete, inspected area on level 4 approved for cover, north of elevator to be completed/inspected at a later date. Rough in inspection for south side level 5 complete, cover is not approved until insulation is installed over piping and passed inspection. North side of elevator on level 5 to be completed/inspected at a later date.
BLD17-01546 FIRE-Final Inspection8/8/20178/9/20178/9/2017 1:24:54 PMPCANC
Inspection request cancelled, space not ready for final life fire safety inspection, office spaces are missing the ceiling tile, ceiling tile provides heat collection for fire sprinkler head operation. Inspection request will be made when ceiling tile is installed and complete.
FIR17-00296 INSP-Final Inspection8/8/20178/9/20178/9/2017 1:21:24 PMPPASS
Rough in inspection complete for overhead fire sprinkler piping/pendant heads, approved for cover. Final fire sprinkler inspection passed/complete.
FIR17-00173 INSP-Sprinkler Rough-in8/7/20178/9/20178/9/2017 10:42:58 AMAPART
Tenting inspection complete, insulating contractor needs to provide documentation for the foam blow in insulation for compatibility with CPVC, cover is approved at builders discretion based on compatability report, if blow in insulation is not compatible then foam covered fire sprinkler piping will need to be replaced.