Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC19-01273 Rough-in8/9/20198/9/20198/9/2019 3:05:12 PMPPASS
request re-inspection at unit 506. Call Project super (Jesse) ahead of time for access: Jesse ###-####. Flexible ducting was changed to rigid pipe. Phone #: ###-#### Inspection requested via web by Mike Almanza
MEC19-03462 Rough-in8/9/20198/9/20198/9/2019 2:45:31 PMPPASS
if questions call Pat @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann - 60lb gas pass
MEC19-01570 Final8/9/20198/9/20198/9/2019 2:25:19 PMPPASS
Contact Steve Tow ###-#### please call 30 minuets prior. Phone #: ###-#### Inspection requested via web by Dan Flaherty
MEC19-01212 Rough-in8/9/20198/9/20198/9/2019 1:35:15 PMPPART
HVAC rough-in hard lid inspection and rough-in fire damper Phone #: ###-#### Inspection requested via web by RM Mechanical - Fire damper clearances okay. Bathroom hard lids okay to cover.
MEC19-03462 Rough-in8/8/20198/9/20198/9/2019 9:16:25 AMAFAIL
If questions call Pat @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann - Need to test at 60lbs on a 100lb gauge, or 20lbs on a 30lb gauge