Inspections for the day of: Wednesday, September 1, 1999.
Number of inspections: 21
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRuss Owen
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD99-02395 INSP - Foundation8/31/19999/1/19999/1/2000 12:00:00 AMAFAIL
09/01/99 407 - they called me to tell me that a suppervisor had given th
BLD99-02512 INSP - Foundation8/31/19999/1/19999/1/1999 12:00:00 AMAFAIL
09/01/99 407 - poured before inspection set backs and work would appear
BLD99-01634 INSP - Framing/Rough-in8/31/19999/1/19999/1/1999 12:00:00 AMANR
09/01/99 407 - need mechanical and foam sealant package.
BLD99-02052 INSP - Framing/Rough-in8/31/19999/1/19999/1/1999 12:00:00 AMAPASS
09/01/99 407 - SHEER PANEL.
BLD99-02073 INSP - Foundation8/31/19999/1/19999/1/1999 12:00:00 AMAFAIL
09/01/99 407 - left corrections.
BLD99-02073 INSP - Foundation8/31/19999/1/19999/1/1999 12:00:00 AMACANC
09/01/99 407 - called in 2 times.
BLD99-02266 INSP - Foundation9/1/19999/1/19999/1/1999 12:00:00 AMPPASS
STEM WALL, CONCRETE MATT ###-####
BLD99-02374 INSP - Foundation9/1/19999/1/19999/1/1999 12:00:00 AMPPASS
bill- ###-#### ft insp
BLD99-01683 INSP - Framing/Rough-in9/1/19999/1/19999/1/1999 12:00:00 AMPPASS
/ / 407 - OK TO COVER .
BLD99-01994 INSP - Framing/Rough-in9/1/19999/1/19999/1/1999 12:00:00 AMPFAIL
09/01/99 407 - need approved plans.
BLD99-02013 INSP - Energy code compliance8/31/19999/1/19999/1/1999 12:00:00 AMPPASS
09/01/99 407 - also framing ok.
MEC99-02205 INSP - Final8/31/19999/1/19999/1/1999 12:00:00 AMPPASS
09/01/99 407 - andrea ###-#### fn insp
MEC99-02205 INSP - Final8/31/19999/1/19999/1/1999 12:00:00 AMPPASS
09/01/99 407 - andrea ###-#### fn insp
MEC99-02346 INSP - Final9/1/19999/1/19999/1/1999 12:00:00 AMPPASS
MEC99-02346 INSP - Final9/1/19999/1/19999/1/1999 12:00:00 AMPPASS
MEC99-02769 INSP - Framing/ Rough-in9/1/19999/1/19999/1/1999 12:00:00 AMPFAIL
09/01/99 407 - re-insp fee.
MEC99-02849 INSP - Framing/ Rough-in9/1/19999/1/19999/1/1999 12:00:00 AMPPASS
09/01/99 407 - DAVE ###-####, R/I, P/T
BLD99-00893 INSP - Energy code compliance9/1/19999/1/19999/1/1999 12:00:00 AMPPASS
09/01/99 407 - JOHN ###-####
BLD99-01423 INSP - Energy code compliance9/1/19999/1/19999/1/1999 12:00:00 AMPPASS
09/01/99 407 - corrections made 1 left in attic will recheck latter.
BLD99-01514 INSP - Final8/31/19999/1/19999/1/1999 12:00:00 AMPFAIL
09/01/99 407 - PERRY ###-####
BLD99-02603 INSP - Foundation9/1/19999/1/19999/1/1999 12:00:00 AMPPASS
090199TE FOOTING MATT ###-####