Inspections for the day of: Wednesday, September 1, 2010.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD10-01223 FIRE-Final Inspection8/31/20109/1/20109/2/2010 5:10:10 PMANR
Project is not in condition for fire life safety final at this time. Partial only for related fire alarm and sprinkler work.
BLD10-01223 FIRE-Alarm Testing8/31/20109/1/20109/2/2010 5:08:31 PMAPART
Alarm testing completed for work finished to date.
FIR10-00250 INSP-Final Inspection8/31/20109/1/20109/2/2010 5:07:38 PMAPART
Fire sprinkler work at the beam rooms are complete- need to verify resubmittals for field modifications. 2nd floor work incomplete at this time.
FIR10-00249 INSP-Alarm Testing8/31/20109/1/20109/2/2010 5:04:39 PMAPART
Completed notification testing at the 1st and 2nd floor per scope of permit work, also tested smoke detection at RF21, 16 and 26. FCU's are not yet installed.
FIR10-00165 INSP-Sprinkler Rough-in9/1/20109/1/20109/1/2010 4:48:20 PMPPART
Scheduled underground flush for the dedicated service supply line.
BLD10-01238 FIRE-Sprinkler Rough-in9/1/20109/1/20109/1/2010 4:43:15 PMPPART
Overhead fire sprinkler work at the remodel area is approved for cover.
BLD06-01629 FIRE-Final Inspection9/1/20109/1/20109/1/2010 4:39:26 PMPPASS
Noted correction field verified for completion, fire life safety final passed.
FIR10-00334 INSP-Sprinkler Rough-in8/31/20109/1/20109/1/2010 11:48:57 AMAPART
Overhead fire sprinkler system modifications per the scope of work on the 18th and 19th floors are approved for cover at the drop ceilings.
FIR02-00024 FIR-Aging Inspection9/1/20109/1/20109/1/2010 11:47:21 AM PASS
Permit activity notes indicate work has been finished.