BLD10-01223
| FIRE-Final Inspection | 8/31/2010 | 9/1/2010 | 9/2/2010 5:10:10 PM | A | NR |
|
|
Project is not in condition for fire life safety final at this time. Partial only for related fire alarm and sprinkler work.
|
BLD10-01223
| FIRE-Alarm Testing | 8/31/2010 | 9/1/2010 | 9/2/2010 5:08:31 PM | A | PART |
|
|
Alarm testing completed for work finished to date.
|
FIR10-00250
| INSP-Final Inspection | 8/31/2010 | 9/1/2010 | 9/2/2010 5:07:38 PM | A | PART |
|
|
Fire sprinkler work at the beam rooms are complete- need to verify resubmittals for field modifications. 2nd floor work incomplete at this time.
|
FIR10-00249
| INSP-Alarm Testing | 8/31/2010 | 9/1/2010 | 9/2/2010 5:04:39 PM | A | PART |
|
|
Completed notification testing at the 1st and 2nd floor per scope of permit work, also tested smoke detection at RF21, 16 and 26. FCU's are not yet installed.
|
FIR10-00165
| INSP-Sprinkler Rough-in | 9/1/2010 | 9/1/2010 | 9/1/2010 4:48:20 PM | P | PART |
|
|
Scheduled underground flush for the dedicated service supply line.
|
BLD10-01238
| FIRE-Sprinkler Rough-in | 9/1/2010 | 9/1/2010 | 9/1/2010 4:43:15 PM | P | PART |
|
|
Overhead fire sprinkler work at the remodel area is approved for cover.
|
BLD06-01629
| FIRE-Final Inspection | 9/1/2010 | 9/1/2010 | 9/1/2010 4:39:26 PM | P | PASS |
|
|
Noted correction field verified for completion, fire life safety final passed.
|
FIR10-00334
| INSP-Sprinkler Rough-in | 8/31/2010 | 9/1/2010 | 9/1/2010 11:48:57 AM | A | PART |
|
|
Overhead fire sprinkler system modifications per the scope of work on the 18th and 19th floors are approved for cover at the drop ceilings.
|
FIR02-00024
| FIR-Aging Inspection | 9/1/2010 | 9/1/2010 | 9/1/2010 11:47:21 AM | | PASS |
|
|
Permit activity notes indicate work has been finished.
|