Inspections for the day of: Wednesday, September 10, 2008.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR08-00293 INSP-Sprinkler Rough-in/Hydro9/10/20089/10/20089/12/2008 11:14:33 AMPPASS
The underground hydro test passed. Ryan asked me to look at the earthquake bracing for the overhead system while I was there. The attachment point on the webbing of the trusses is not allowed unless a structural engineer approves it. If not the attachment point is to be at the top of the structure.
BLD08-01594 FIRE-Final Inspection9/9/20089/10/20089/10/2008 5:09:05 PMPPASS
Life safety passed
FIR08-00556 INSP-Sprinkler Rough-in9/10/20089/10/20089/10/2008 3:35:38 PMPPASS
The overhead sprinkler pipin can be covered.
BLD07-02106 FIRE-Final Inspection9/10/20089/10/20089/10/2008 3:05:38 PMPFAIL
The exit signs and exit discharge lights have not been repaired.
FIR08-00490 INSP-Final Inspection9/9/20089/10/20089/10/2008 1:17:37 PMAPASS
Permit finaled
FIR08-00307 INSP-Final Inspection9/9/20089/10/20089/10/2008 1:17:17 PMACANC
This inspection is to be rescheduled with the fire alarm testing.