Inspections for the day of: Monday, September 10, 2012.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorClint A Smith
TitleEROSION CONTROL INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC11-00884 BMP Violation9/10/20129/10/20129/10/2012 9:57:34 PMPFAIL
RP explained that the final landscape and the driveway will be complete by mid this week. I explained to him that even though the projet is almost complete, that he must still remove the nylon silt fence screening out of the storm drain and place in an approved storm drain inlet protection, (ex: silt saver, blocksom, or a dandy bag). Will inspect on 9/12/2012 11AM for project status.
ESC11-00176 General Inspection9/10/20129/10/20129/10/2012 2:59:05 PM FAIL
Verbal to RP:
Clean up all sediment residual out of the gutter pans and maintain the storm drain inlet in the corner of Epsilon and Deer Forked.
ESC11-00590 General Inspection9/10/20129/10/20129/10/2012 1:21:34 PM PASS
ESC11-00517 General Inspection9/10/20129/10/20129/10/2012 1:21:22 PM PASS
ESC11-00518 General Inspection9/10/20129/10/20129/10/2012 1:21:10 PM PASS
ESC12-00910 Site Preparation9/10/20129/10/20129/10/2012 1:20:30 PM PASS
ESC11-00580 General Inspection9/10/20129/10/20129/10/2012 1:19:00 PM DONE
PErmit finaled.
ESC11-00580 DOC - Permit Finaled9/10/20129/10/20129/10/2012 1:18:50 PMPPASS
ESC10-00822 Aging Inspection9/10/20129/10/20129/10/2012 1:17:47 PM PASS
ESC11-00408 General Inspection9/10/20129/10/20129/10/2012 1:17:04 PM PASS
ESC12-00403 General Inspection9/10/20129/10/20129/10/2012 9:18:39 AMPPART
At time time of 08:40 am, the discharge into the storm drain inlet off of Myrtle appears to be clean. Still waiting on lab results from Strata on the first intial samples. Also waiting on ACHD to give a background NTU level for what samples must be based off of to meet the water quality standards for the state of Idaho. Due to dewatering activities occuring for a potental period of more than ten days, the turbidity cannot exceed over 20 NTU's based upon background.