Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC13-00887 Site Preparation9/4/20139/4/2013 P 
jeff Phone #: ###-####
ESC13-00555 General Inspection9/6/20139/6/2013   
BLD13-01285 BLD-Footing9/9/20139/10/20139/10/2013 2:56:16 PMPCANC
Phone #: 2086971241 >> Inspection requested via mobile web by Heron. Wrong permit called in.
ESC13-00750 BMP Violation9/10/20139/10/20139/10/2013 2:55:39 PMPPART
Sweep all silts from hard surfaces
ESC13-00752 BMP Violation9/10/20139/10/20139/10/2013 2:55:05 PMPPART
Sweep all silts from hard surfaces
ESC13-00762 BMP Violation9/10/20139/10/20139/10/2013 2:54:34 PMPPART
Sweep all silts from hard surfaces.
BLD13-02048 BLD-Energy code compliance9/10/20139/10/20139/10/2013 2:53:38 PMPPASS
steve Phone #: ###-####. rigid insulation at interior side of stemwall under slab on grade
BLD13-02056 BLD-Energy code compliance9/10/20139/10/20139/10/2013 2:52:47 PMPPASS
steve Phone #: ###-####. rigid insulation at interior side of stemwall under slab on grade
BLD13-02055 BLD-Energy code compliance9/10/20139/10/20139/10/2013 2:51:43 PMPPASS
steve Phone #: ###-####. rigid insulation at interior side of stemwall under slab on grade.
BLD13-02212 BLD-Footing9/10/20139/10/20139/10/2013 1:32:32 PMPPASS
chachos Phone #: ###-####
BLD13-01289 BLD-Wall Bracing9/10/20139/10/20139/10/2013 1:02:38 PMAPASS
Sheer Phone #: ###-#### >> Inspection requested via web by Mike McHargue. 1st, 2nd and 3rd floor exterior shearwalls ok. ok to cover exterior of building.
BLD13-02387 BLD-Other9/9/20139/10/20139/10/2013 10:36:47 AMAPASS
MH Setup Phone #: ###-#### >> Inspection requested via web by Richard Estes. block and tie only ok.
GCB13-00089 GCB-Framing9/9/20139/10/20139/10/2013 9:09:07 AMAPART
###-#### courtesy inspection. Will special inspection on welding for added beam. Refer to architect regarding elevation changes for sidewalk at north side of building. Ok to one side ofter rough ins are complete and inspected.
BLD13-01285 BLD-Foundation9/6/20139/10/20139/9/2013 3:04:59 PMPCANC
Phone #: 2086971241 >> Inspection requested via mobile web by Heron Inspection cancelled via mobile web on Monday, September 09, 2013.