FIR14-00177
| INSP-Supply line flush | 9/10/2014 | 9/10/2014 | 9/10/2014 3:31:32 PM | P | PASS |
|
|
Underground flush passed
|
FIR14-00339
| INSP-Sprinkler Rough-in | 9/9/2014 | 9/10/2014 | 9/10/2014 3:31:00 PM | P | PASS |
|
|
24 hour air test passed
|
FIR14-00367
| INSP-Sprinkler Rough-in | 9/9/2014 | 9/10/2014 | 9/10/2014 1:53:29 PM | A | PASS |
|
|
Rough-in passed. Plan modifications are needed due to additional branchlines and heads added because of structural members. 24 hour air test started at 1:00 with pressure marked on guage.
|
FIR14-00300
| INSP-Sprinkler Rough-in/Hydro | 9/5/2014 | 9/10/2014 | 9/10/2014 10:16:25 AM | A | CANC |
|
|
Wrong permit number called in.
|
FIR14-00300
| INSP-Supply line flush | 9/5/2014 | 9/10/2014 | 9/10/2014 10:04:06 AM | A | CANC |
|
|
Wrong permit number called in.
|
BLD14-01807
| FIRE-Final Inspection | 9/8/2014 | 9/10/2014 | 9/10/2014 9:10:28 AM | A | PASS |
|
|
life safety passed
|
FIR14-00613
| INSP-Final Inspection | 9/9/2014 | 9/10/2014 | 9/10/2014 9:09:44 AM | A | PASS |
|
|
Permit finaled
|
FIR14-00660
| INSP-Final Inspection | 9/10/2014 | 9/10/2014 | 9/10/2014 8:39:19 AM | P | CANC |
|
|
Would like to schedule in conjunction with fire life safety final for BLD. Please call Jon with time frame. Phone #: ###-#### >> Inspection requested via web by Jeff Packham Inspection cancelled from web by: Jeff Packham
|
FIR14-00474
| INSP-Sprinkler Rough-in | 9/9/2014 | 9/10/2014 | 9/10/2014 8:18:17 AM | A | PASS |
|
|
See the city approved plans for "Entry" marked on the plans as OK to cover.
|
FIR14-00444
| INSP-Sprinkler Rough-in | 9/9/2014 | 9/10/2014 | 9/10/2014 7:22:33 AM | A | PASS |
|
|
Tenting is complete. Piping can be covered.
|